Harris Corporation
Case: B-274566
Agency:
Protester: Harris Corporation
Date: 1996-11-27
Denied
Harris Corporation
BNUMBER: B-274566; B-274566.2
DATE: November 27, 1996
TITLE: Harris Corporation
**********************************************************************
Matter of:Harris Corporation
File: B-274566; B-274566.2
Date:November 27, 1996
Dorn C. McGrath III, Esq., and Richard L. Moorhouse, Esq., Holland &
Knight, for the protester.
Kenneth S. Kramer, Esq., and Nancy R. Wagner, Esq., Fried, Frank,
Harris, Shriver & Jacobson, for Raytheon Electronic Systems, Raytheon
Company, an intervenor.
Vera Meza, Esq., and Walter Harbort, Jr., Esq., Department of the
Army, for the agency.
Linda S. Lebowitz, Esq., Office of the General Counsel, GAO,
participated in the preparation of the decision.
DIGEST
Where the solicitation required offerors to propose fixed prices and
provided that options, if exercised, would not necessarily be
exercised in a manner to guarantee continuous production, and where
the protester states in its best and final offer, after discussions
regarding these requirements, that it reserved the right to recover
additional costs associated with breaks in production in the option
periods, the protester's proposal is properly rejected as technically
unacceptable since the firm took exception to the solicitation's
material fixed-price and option requirements.
DECISION
Harris Corporation protests the award of a contract to Raytheon
Electronic Systems, Raytheon Company, under request for proposals
(RFP) No. DAAB07-96-R-A509, issued by the Department of the Army for
the fabrication, integration, test, and delivery of Tri-Band Tactical
Terminals (T3(H)s) for battlefield satellite terminal communications.
Harris challenges the rejection of its proposal as technically
unacceptable.
We deny the protests.
The RFP contemplated the award of a firm, fixed-price contract for the
T3(H) units for a basic contract period and five 24-month option
periods to the offeror whose proposal represented the best value to
the government, technical evaluation factors, price, and performance
risk considered.[1] As relevant to these protests, the RFP included
clause H-4, captioned "Option for Increased Quantity--Separately
Priced Line Item." Paragraph (e) of this clause provides that the
"[e]valuation of options will not obligate the Government to exercise
the option(s)," and paragraph (g) provides that:
"[t]he Government may exercise subsequent options if prior option
years are not exercised (i.e. [(sic)] if the Government does not
exercise Option I, the Government still has the right to exercise
Option II). Exercise of subsequent years is not dependent upon
exercise of the prior year option."
In its initial proposal, submitted in April 1996, under a section
captioned "Other Conditions and Assumptions," Harris addressed clause
H-4, stating that:
"The prices for the Option Period hardware CLINS/SLINS do not
contain startup or non-recurring cost[s] provided for in the
basic period, but are dependent upon steady work flowing through
the T3(H) Focused Factories. Consequently, Harris reserves the
right to recover cost[s] associated with breaks in the T3(H)
production flow associated with loss of learning, idle resources
and personnel disruptions." (Emphasis added.)
By letter dated June 24, the contracting officer notified Harris that
the agency had completed its initial evaluation. The contracting
officer enclosed with this letter, among other things, items for
negotiation (IFN) and responses to Harris's terms and conditions.
With regard to the above quoted condition in Harris's initial
proposal, the contracting officer stated that:
"The Government does not warrant that options will be exercised
so as to facilitate a steady production flow. As stated in RFP
Section H-4, Option for Increased Quantity--Separately Priced
Line Item, option quantities are not guaranteed and the 'exercise
of subsequent [option] years is not dependent upon exercise of
the prior year option.'" (Emphasis added.)
The contracting officer also enclosed with her June 24 letter a model
contract for Harris, explaining that "if [Harris] is the successful
offeror, [Harris] will be required to sign this document. Therefore,
please review the model contract and provide comments as necessary
with your IFN responses." Harris's model contract contained RFP
clause H-4, "Option for Increased Quantity--Separately Priced Line
Item," including paragraphs (e) and (g) as quoted above.[2] In
addition, in response to a previous question posed by Harris
concerning the submission of alternate proposals, the contracting
officer responded that "alternate proposals are acceptable with the
exception of: a) an alternate proposal that changes the contract
type." The contracting officer afforded Harris an opportunity to
revise its proposal by submitting proposal revision change pages.
Full decision text continues on ProtestIntel...