Matter of:Alliant Techsystems, Inc.
Case: B-276162
Agency:
Protester: Matter of:Alliant Techsystems, Inc.
Date: 1997-05-02
Denied
Matter of:Alliant Techsystems, Inc.
BNUMBER: B-276162; B-276162.2; B-276162.3
DATE: May 2, 1997
TITLE: Matter of:Alliant Techsystems, Inc.
**********************************************************************
DOCUMENT FOR PUBLIC RELEASE
A protected decision was issued on the date below and was subject to a
GAO Protective Order. This version has been redacted or approved by
the parties involved for public release.
Matter of:Alliant Techsystems, Inc.
File: B-276162; B-276162.2; B-276162.3
Date:May 2, 1997
John S. Pachter, Esq., Jonathan D. Shaffer, Esq., Eun K. (Julie)
Chung, Esq., and Dorothy E. Terrell, Esq., Smith, Pachter, McWhorter &
D'Ambrosio, P.L.C., for the protester.
Thomas J. Madden, Esq., Jerome S. Gabig, Jr., Esq., Fernand A.
Lavallee, Esq., and John J. Pavlick, Jr., Esq., Venable, Baetjer,
Howard & Civiletti, and Scott W. MacKay, Esq., in-house counsel, for
Lockheed Martin Corporation, an intervenor.
Gregory H. Petkoff, Esq., and John E. Lariccia, Esq., Department of
the Air Force, for the agency.
Paul E. Jordan, Esq., and Paul Lieberman, Esq., Office of the General
Counsel, GAO, participated in the preparation of the decision.
DIGEST
1. In assessing proposals for multi-year production contract which
contemplates technology inserts over course of performance, agency
evaluation of awardee's proposed insert component which is not yet
developed, including review of proposal, technical briefings, and
parallel development by other manufacturers, is unobjectionable where
agency reasonably concludes that component ultimately will be
successfully produced. Because agency has right to reject component
from introduction as technology insert if it does not meet all
specifications, agency reasonably determined that only potential
impact of insert component on procurement will be to cost and schedule
and thus, properly determined to evaluate component under
affordability evaluation factor.
2. In procurement with cost and fixed-price elements, where offerors
are committed to meet or better proposed system-life average unit
prices (AUP) or face substantial penalties, agency's affordability
evaluation is reasonable where it includes appropriate assessment of
realism, reasonableness, and completeness of proposed costs which
underlie AUP in accordance with evaluation criteria.
3. Award decision is unobjectionable where protester's slight
advantage in "instant" contract cost and lower prices through earlier
phases of procurement life is outweighed by selected offeror's
technical advantages and significantly lower proposed prices over life
of procurement.
DECISION
Alliant Techsystems, Inc. protests the Department of the Air Force's
downselection and award of the Wind Corrected Munitions Dispenser
(WCMD) Pilot Production Option under contract No. F08626-95-C-0106,
P00010 to Lockheed Martin Corporation. Alliant contends that the
agency's technical and cost evaluations were flawed and that the
source selection authority's best value decision failed to take
certain risk and cost factors into account.
We deny the protest.
BACKGROUND
The WCMD is a modification kit that replaces the tail sections on a
portion of current inventory cluster munitions. The kit will enable
the tail dispensers which carry the cluster munitions to correct for
the effects of launch transients, ballistic errors, and unknown winds
between the release point and the dispenser's functioning point.
Alliant and Lockheed were each awarded 24-month contracts in January
1995, to perform engineering and manufacturing development (EMD) of
the WCMD on a cost-plus-fixed fee basis. In accordance with the terms
of these contracts, the Air Force issued a call for
improvements/request for proposals (CFI/RFP) to each offeror to submit
updated proposals for the 20-month pilot production phase and optional
low-rate initial production lots (LRIPs 1 and 2), and prices for three
full rate production lots (FRP). The solicitation contemplated award
of only the pilot production option to one contractor, but reserved
the right to exercise the options with both EMD contractors, or to
make no option award at all. Exercise of the LRIP 1 option was to be
made not later than 14 months after award of the pilot production
option and LRIP 2 not later than 14 months after the exercise of LRIP
1. Timing of the FRP awards was not included in the CFI/RFP.
Clause H.16 of both EMD contracts sets forth four evaluation areas in
descending order of importance: affordability, technical, management,
and instant contract cost. General considerations also were to be
evaluated, but were of lesser importance than the specified criteria.
Clause H.16 also identified evaluation factors under three of the four
criteria.
Full decision text continues on ProtestIntel...