Grot, Inc., B-276979.2; B-277463, August 14, 1997
Case: B-276979.2
Agency:
Protester: Grot, Inc., B
Date: 1997-08-14
Denied
Grot, Inc., B-276979.2; B-277463, August 14, 1997
BNUMBER: B-276979.2; B-277463
DATE: August 14, 1997
TITLE: Grot, Inc., B-276979.2; B-277463, August 14, 1997
**********************************************************************
Matter of:Grot, Inc.
File: B-276979.2; B-277463
Date:August 14, 1997
Andrew J. Kilpatrick, Jr., Esq., Hickman, Sumners, Goza & Gore, for
the protester.
Joseph A. Gonzales, Esq., and Larry E. Beall, Esq., Department of the
Army, for the agency.
Linda C. Glass, Esq., and Paul I. Lieberman, Esq., Office of the
General Counsel, GAO, participated in the preparation of the decision.
DIGEST
Agency properly canceled invitation for bids after bid opening where
the solicitation specifications did not adequately set forth the
agency's requirements, and prior to bid opening, the agency had
provided only one of several offerors with informal clarifications
regarding the actual requirements.
DECISION
Grot, Inc. protests the cancellation after bid opening of invitation
for bids (IFB)
No. DACA01-97-B-0033, issued by the Department of the Army, Corps of
Engineers, and the resolicitation of the same requirement for upgrade
of fire protection at Arnold Air Force Base, Tennessee.
We deny the protests.
The procurement is for the addition and/or replacement of fire
protection devices and fire alarm systems in several buildings at
Arnold Air Force Base. The specifications included requirements for
heat and smoke detectors, fire alarm panels, horns and miscellaneous
appurtenances. The successful firm was to perform all work and
furnish all plant, labor, equipment, and materials required by the
specifications and drawings. The IFB consisted of 17 base bid items
and 6 option items, each separately priced. The IFB contemplated the
award of a fixed-price contract to the responsible bidder submitting
the low responsive bid on the base items and all options items.
Four bids were received by the April 29 bid opening, ranging from
$1,322,807 to $3,017,218. The government estimate was $1,285,214.
Grot's bid of $2,282,000 became low after the apparent low bidder
claimed a mistake in bid and was allowed to withdraw its bid. When
the agency compared the three remaining bids with the government's
estimate, it concluded that none of them was in the "awardable range"
(presumably meaning that none was at a reasonable price).
The agency subsequently examined the solicitation and determined that
the specifications were ambiguous. For example, the agency concluded
that the following specifications were defective:
1. Specification 16721 did not clearly define the scope of work
and ambiguities existed between plans and specifications.
2. Neither the drawings nor specifications clearly indicate the
scope of work in testing the existing fire alarm/detection
system.
3. The scope of work for the removal of lead paint was not
clearly defined in the solicitation.
4. The scope of work was not clearly defined for additions to or
replacement of existing fire alarm/detection systems devices for
numerous buildings.
5. The drawing for Building 895 required a new fire alarm
control panel and radio transmitter, but did not indicate the
number of zones.
Accordingly, the agency determined that the system design had to be
clarified to ensure accurate understanding of the scope of work by
bidders and concluded that this constituted a compelling reason to
cancel the IFB. The bidders were notified of the cancellation by
letter dated May 28. The specifications were revised and a new
solicitation was issued on June 20 with a July 22 bid opening date.[1]
Grot asserts that the agency lacked a compelling reason to cancel
because the IFB did not contain ambiguous or defective specifications.
The protester maintains that the plans and specifications were
sufficiently clear to permit the government to estimate the cost of
the work, as well as to permit four firms to formulate and submit bids
on the project.
While Grot appears to concede that the resolicitation issued on June
20, for which the government estimate is $2,000,000, addressed these
ambiguities and also added a requirement for a supervisor, Grot takes
the position that these clarifications and changes are insignificant.
With respect to the clarification of the scope of required lead paint
abatement activity by the contractor, Grot contends that this simply
codifies its understanding of this provision. It is the protester's
position that the scope of lead paint abatement is clearly defined by
the specifications, which require only the area of paint which is
disturbed to be abated.
Full decision text continues on ProtestIntel...