Marvin J. Perry & Associates, B-277684; B-277685, November 4,
Case: B-277684
Agency:
Protester: Marvin J. Perry & Associates, B
Date: 1997-11-04
Sustained
Marvin J. Perry & Associates, B-277684; B-277685, November 4,
BNUMBER: B-277684; B-277685
DATE: November 4, 1997
TITLE: Marvin J. Perry & Associates, B-277684; B-277685, November 4,
1997
**********************************************************************
Matter of:Marvin J. Perry & Associates
File: B-277684; B-277685
Date:November 4, 1997
Malcolm D. Wilson for the protester.
Georgia Vlahos, Esq., and Kenneth J. Densmore, Esq., Department of the
Navy, for the agency.
Charles W. Morrow, Esq., and James A. Spangenberg, Esq., Office of the
General Counsel, GAO, participated in the preparation of the decision.
DIGEST
Modifications of orders under General Services Administration Federal
Supply Schedule for red oak sleeping room furniture to allow a change
in the type of wood to ash, which is less expensive than red oak,
materially changed the nature of the orders from those originally
issued and thereby prejudiced the protester, a competing vendor.
DECISION
Marvin J. Perry & Associates protests the modifications of delivery
order No. GS-27-F-028B and purchase order No. N00210-96-M-0566, issued
by the Department of the Navy, Naval Training Center, Great Lakes,
Illinois, to DCI for red oak sleeping room furniture. Perry
essentially contends that the modifications were beyond the scope of
these orders.
We sustain the protest.
This procurement was for 563 10-piece sets of red oak sleeping room
furniture to furnish a bachelor enlisted quarters (BEQ) that was under
construction. Prior to the procurement, the Navy contracted with an
architectural firm to design the interior space for the project. The
firm recommended Perry as the vendor holding a General Services
Administration (GSA) Federal Supply Schedule (FSS) contract offering
the lowest-priced red oak furniture that met the functional needs of
the agency with respect to aesthetics and quality.[1] In order to
ensure that Perry's products represented the best value, the Navy
decided to solicit quotes from those vendors with similar products on
the FSS.
Only 9 of the 10 pieces of each set could be obtained from the FSS,
and on April 1, 1996, the Navy solicited quotes for these 9 pieces of
red oak furniture under request for quotations (RFQ) No.
N00210-96-Q-1496. On that same date, quotes were solicited for the
remaining piece--the red oak footboard to the bed--under RFQ No.
N00210-96-Q-1497.[2]
The Navy received eight quotes for the nine pieces of furniture and
six quotes for the footboard by the May 30 closing dates. DCI
submitted the lowest quote of $557,127.91 for the nine items; Perry
was next low with a quote of $572,709. Perry submitted the lowest
quote of $18,016 for the footboard; DCI submitted the next lowest
quote of $19,789.45. Since DCI's quotes reflected the lowest total
price, the Navy issued the delivery order from the FSS for the nine
pieces to DCI on June 11 and the purchase order for the footboard to
DCI on June 18. The original delivery date for the furniture was
scheduled for September 30, but several construction delays resulted
in the delivery date being pushed back to June 9, 1997.
In May 1997, DCI advised the Navy that its supplier had mistakenly
delivered ash instead of red oak. Because of this, DCI proposed that
the Navy either accept furniture made with ash at the same price or
postpone the delivery date. In support of accepting ash furniture,
DCI provided the Navy with samples of ash stained to match the color
of red oak. After comparing the samples with the red oak furniture
already in the BEQ, the Navy determined that the ash furniture was an
acceptable substitute. The parties agreed to the substitution on May
19. The Navy accepted delivery of the ash furniture in June.
In late June, Perry learned that the Navy had permitted DCI to
substitute ash furniture for red oak furniture. Perry initially
sought an explanation from the agency by letter dated June 30, in
which it complained that changing the wood from red oak to ash would
be unfair to those quoters who based their quotes on providing
furniture made from red oak, because ash is a lower grade and lower
priced wood, and that if "there was no authorization" to change the
wood, the Navy should reject DCI's furniture and make award to the
next low quoter--Perry. The Navy responded by letter dated July 21
(received by the protester on July 25) asserting that the change was
insignificant. On August 4, Perry protested the Navy's actions to our
Office.
The Navy initially argues that the August 4 protest is untimely
because it was filed more than 10 working days after late June when
the protester knew of the basis of protest. We disagree. Although
the protester's June 30 letter to the agency was not expressly
characterized as a protest, we will treat it as an agency-level
protest because it clearly conveyed an expression of dissatisfaction
and a request for corrective action.
Full decision text continues on ProtestIntel...