Southern Technologies, Inc., B-278030; B-278030.2, December
Case: B-278030
Agency:
Protester: Southern Technologies, Inc., B
Date: 1997-12-19
Denied In Part
Southern Technologies, Inc., B-278030; B-278030.2, December
BNUMBER: B-278030; B-278030.2
DATE: December 19, 1997
TITLE: Southern Technologies, Inc., B-278030; B-278030.2, December
19, 1997
**********************************************************************
Matter of:Southern Technologies, Inc.
File: B-278030; B-278030.2
Date:December 19, 1997
James V. Etscorn, Esq., Baker & Hostetler, for the protester.
Charles G. Lill for Frank Lill & Son, Inc., an intervenor.
Ann Giddings, Esq., and Lis B. Young, Esq., Naval Facilities
Engineering Command, for the agency.
Jennifer Westfall-McGrail, Esq., and Christine S. Melody, Esq., Office
of the General Counsel, GAO, participated in the preparation of the
decision.
DIGEST
Protester's objection to corrective action proposed by contracting
agency in response to protest--i.e., paying protester's proposal
preparation costs--is without merit where, although agency
acknowledges that the solicitation specifications were misleading,
agency demonstrates that, due to urgency of the requirement, alternate
corrective action requested by protester--recompeting with revised
specifications--is not feasible.
DECISION
Southern Technologies, Inc. objects to the corrective action proposed
by the Department of the Navy in response to Southern's protest of the
rejection of its proposal under request for proposals (RFP) No.
N62477-97-R-0041. The Navy decided not to reopen the competition, as
requested by Southern, but instead to pay Southern its proposal
preparation costs as compensation for the agency's improper actions in
conducting the procurement. The protester contends that the agency
should reopen the competition since reopening is a practicable, and
more meaningful, remedy for the impropriety that occurred.
We deny the protest in part and dismiss it in part.
BACKGROUND
The RFP, which was issued on May 28, 1997, solicited proposals for
power plant improvements at the Goddard Power Plant in Indian Head,
Maryland. The purpose of the improvements is to bring the plant,
which is a major emitter of nitrogen oxides (NOx), into compliance
with emission standards set by the state of Maryland. Work to be
performed includes the installation of low NOx coal/oil fired burners
with combustion controls on each of the plant's three boilers, plant
controls, a burner management system, and incidental related work.
The bid schedule divided the work among a base item and two options.
The base item encompassed the entire project, with the exception of
the work described in the option items. Option 1 was for plant
controls, and option 2 was for the work involving the second and third
boilers.
The solicitation provided for the evaluation of proposals on the basis
of price, technical/management factors, and past performance, with
price carrying greater weight in the selection process than the latter
two factors. Technical/management factors included relevant
experience, technical methodology, project staffing, work plan, and
subcontracting plan. Under the technical methodology subfactor,
offerors were to describe the burners that they intended to install
and to submit documentation demonstrating the burners' compliance with
performance criteria identified in the RFP.
Six offerors, including Southern, submitted proposals by the July 25
closing date. The technical evaluation panel determined that the
protester's proposal was technically unacceptable because Southern had
proposed burners employing over-fire air (OFA) combustion, a
technology that the panel considered to be unduly risky and thus
unacceptable. Another proposal was rejected as technically
unacceptable for proposing the same technology.[1] The four remaining
proposals were included in the competitive range.
After a pre-award debriefing at which it was informed of the basis for
the exclusion of its proposal from the competitive range, Southern
protested to our Office, arguing that the OFA technology that it had
proposed was consistent with the solicitation's requirements and that
its proposal ought therefore not to have been excluded from further
consideration.[2]
The Navy responded that its technical experts had considered and
rejected OFA as an acceptable compliance technology prior to issuance
of the RFP. The agency conceded that the RFP's specifications, as
written, could have misled offerors regarding the acceptability of OFA
technology, however, and accordingly, proposed to take corrective
action. The Navy maintained that the corrective action requested by
the protester--i.e., inclusion of its proposal in the competitive
range--was not appropriate, however, because Southern would have to
rewrite its proposal using a different technical approach to make the
proposal susceptible of award. The Navy therefore proposed instead to
reimburse Southern for its proposal preparation expenses.
Full decision text continues on ProtestIntel...