Technology Services International, Inc., B-278050, November
Case: B-278050
Agency:
Protester: Technology Services International, Inc., B
Date: 1997-11-25
Denied
B-278050
Nov 25, 1997
Jump To
VIEW DECISION
RELATED PAGES
GAO CONTACTS
Highlights
DIGEST Apparent low bid was properly rejected as materially unbalanced where the bid. The successful contractor will provide telephone switchboard services 24 hours a day. Bidders were informed that the agency would evaluate bids by adding the prices bid for the base and option periods. Which cautions that a bid may be rejected as nonresponsive if the prices are materially unbalanced. [1] The agency received 17 bids by the bid opening date. 200 The agency concluded that TSI's overall low bid was mathematically and materially unbalanced and rejected TSI's bid in accordance with the terms of the solicitation. Award was made to TECHSECO as the bidder submitting the lowest-priced. The bid must be evaluated mathematically to determine whether the bid is based on understated prices for some work and overstated prices for other work.
View Decision
Matter of: Technology Services International, Inc. File: B-278050 Date: November 25, 1997
DIGEST
Attorneys
DECISION
Technology Services International, Inc. (TSI) protests the rejection of its bid as materially unbalanced and the award of a contract to TECHSECO, Inc., under invitation for bids (IFB) No. F09607-97-B0017, issued by the Department of the Air Force for telephone operator services at Moody Air Force Base, Georgia.
We deny the protest.
The IFB provided for the award of a firm, fixed-price contract for a base with 4 option years. The successful contractor will provide telephone switchboard services 24 hours a day, 7 days a week. The bid schedule required bidders to submit, for each period of the contract, a unit price for the services per month, and an extended price for the services per year. Bidders were informed that the agency would evaluate bids by adding the prices bid for the base and option periods. The IFB also included the standard "Contract Award - Sealed Bidding" clause, set forth at Federal Acquisition Regulation (FAR) Sec. 52.214-10, which cautions that a bid may be rejected as nonresponsive if the prices are materially unbalanced. [1]
The agency received 17 bids by the bid opening date, with TSI and TECHSECO submitting the lowest-priced bids as follows:
TSI TECHSECO
Base Year $142,920 $116,640 1st Option $130,800 $116,640 2nd Option $ 89,760 $116,640 3rd Option $ 77,760 $116,640 4th Option $ 77,760 $116,640
Total $519,000 $583,200
The agency concluded that TSI's overall low bid was mathematically and materially unbalanced and rejected TSI's bid in accordance with the terms of the solicitation. Award was made to TECHSECO as the bidder submitting the lowest-priced, responsive bid, and this protest followed.
An examination of bid unbalancing has two aspects. First, the bid must be evaluated mathematically to determine whether the bid is based on understated prices for some work and overstated prices for other work. The second aspect--material unbalancing--involves an assessment of the cost impact of a mathematically unbalanced bid. Where there is reasonable doubt that award to the bidder submitting the mathematically unbalanced bid would result in the lowest ultimate cost to the government, the bid is materially unbalanced and may not be accepted. FAR Sec. 14.404-2(g), 52.214-10(e); Westbrook Indus., Inc., 71 Comp.Gen. 139, 140 (1992), 92-1 CPD Para. 30 at 4; Solon Automated Servs., Inc., B-206449.2, Dec. 20, 1982, 82-2 CPD Para. 548 at 3.
With regard to service contracts that involve the evaluation of base and option periods, and where the level of service for each period is essentially the same, a large price differential between the base and option periods, or between one option period and another, is prima facie evidence of mathematical unbalancing. Westbrook Indus., Inc., supra, at 3; Professional Waste Sys., Inc.; Tri-State Servs. of Texas, 67 Comp.Gen. 68, 70 (1987), 87-2 CPD Para. 477 at 3. However, the assessment of whether a bid is mathematically unbalanced does not merely involve a comparison of the percentage difference between the base and option period prices. The determinative question is whether the pricing structure is reasonably related to the actual costs to be incurred in each year of the contract. FAR Sec. 52.214-10(e); Residential Refuse Removal, Inc., 72 Comp.Gen. 68, 70 (1992), 92-2 CPD Para. 444 at 4.
Here, TSI's base year price is 59 percent higher than its price for the second option period, and 84 percent higher than its price for either the third or fourth option periods. Because the level of services required during each year of this contract is the same, this significant difference in TSI's prices indicates that its bid is mathematically unbalanced. See Residential Refuse Removal, Inc., supra, at 3-4. Moreover, TSI has not shown that its bid's pricing structure is reasonably related to the actual costs to be incurred in each year of the contract.