Day & Zimmermann/IMR L.L.C., B-280568; B-280569, October 19,
Case: B-280568
Agency:
Protester: Day & Zimmermann/IMR L.L.C., B
Date: 1998-10-19
Denied
Day & Zimmermann/IMR L.L.C., B-280568; B-280569, October 19,
BNUMBER: B-280568; B-280569
DATE: October 19, 1998
TITLE: Day & Zimmermann/IMR L.L.C., B-280568; B-280569, October 19,
1998
**********************************************************************
DOCUMENT FOR PUBLIC RELEASE
The decision issued on the date below was subject to a GAO Protective
Order. This redacted version has been approved for public release.
Matter of:Day & Zimmermann/IMR L.L.C.
File:B-280568; B-280569
Date:October 19, 1998
Stephen G. Anderson, Esq., Baker, Donelson, Bearman & Caldwell, for
the protester. Brian A. Mizoguchi, Esq., Verner Liipfert Bernhard
McPherson and Hand, for Royal Ordnance North America, Inc., an
intervenor.
Bradley J. Crosson, Esq., and Vera Meza, Esq., U.S. Army Materiel
Command, for the agency.
Andrew T. Pogany, Esq., and John M. Melody, Esq., Office of the
General Counsel, GAO, participated in the preparation of the decision.
DIGEST
Award to offeror submitting higher-priced, technically superior
proposal under a solicitation which stated that proposed price was
more important than technical evaluation factors was unobjectionable
where agency reasonably determined that the awardee's substantial
technical advantage warranted payment of the price premium associated
with its proposal.
DECISION
Day & Zimmermann/IMR L.L.C. (D&Z) protests the award of contracts to
Royal Ordnance North America, Inc. (RONA) under request for proposals
(RFP) Nos. DAAA09-97-R-0044 (RFP-0044) and DAAA09-98-0214 (RFP-0214),
issued by the Department of the Army for explosives and a facility use
contract for Holston Army Ammunition Plant (HSAAP), respectively. D&Z
principally argues that the agency misevaluated the proposals, and
made improper awards based on a defective price/technical tradeoff.
We deny the protest.
BACKGROUND
Both solicitations were issued as two-step negotiated procurements.
RFP-0044 sought proposals to award a fixed-price contract for RDX/HMX
explosives and other products for 5 years. RFP-0214 sought proposals
to award a fixed-price facility use contract for HSAAP for a 25-year
period. The solicitations were issued together, contained, as
amended, identical section M evaluation provisions, and provided that
both contracts would be awarded to the same offeror. (For the sake of
simplicity, we therefore will refer to the solicitations as a single
RFP.)[1]
The RDX/HMX products are used by all Department of Defense (DOD)
services. Because of the unique nature of RDX/HMX, such as requiring
large amounts of acid production and recycling, and the commonality of
the RDX/HMX in numerous end item applications, RDX/HMX has been
procured as a bulk item. AR, Tab E, at 3. Due to the large quantity
of RDX/HMX necessary in wartime, HSAAP was constructed in the 1940's
for the sole purpose of manufacturing large quantities of explosives.
HSAAP has been operated as a government-owned, contractor-operated
(GOCO) facility since its completion. Due to declining peacetime
requirements for the RDX/HMX products, the agency found that the cost
of maintaining HSAAP with only these requirements in production had
become cost prohibitive to the Army and its customers. The agency
therefore decided to solicit industry's expertise in finding a
solution to its problem, that is, to "compete the problem." AR, Tab
1, at 3.
On May 5, 1997, a pre-solicitation conference was held at which
industry was provided with the definition of the "problem," a
description of the proposed acquisition, a discussion of the
requirements, both peacetime and replenishment,[2] a presentation on
the availability of Armament Retooling and Manufacturing Support
(ARMS) funding, and a description of the facility at HSAAP, among
other things. The problem as defined at this conference remained the
same throughout the final selection of the successful contractor. The
problem had four parts: (1) peacetime requirements for RDX/HMX; (2)
replenishment requirements for these items; (3) need for development
of new formulations of explosives, defined as research and development
(R&D); and (4) a plan for the HSAAP facility itself, comprised of
approximately 6,000 acres of acid manufacturing and explosives
finishing equipment and buildings. AR, Tab C. In response,
contractors then furnished "concept papers," which were unique to each
contractor. AR, Tab 1, at 3. Because of the uniqueness of the
contractor approaches, the agency decided to "'cut' a competitive
range," so the agency could logically handle unique performance-based
contracts and still maintain a competitive basis. AR, Tab 1, at 4.
Consequently, on August 1, 1997, the agency issued the first-step
solicitation for the purpose of establishing a competitive range of
the "technically acceptable offerors that will move on to the second
and final step." AR, Tab F, at 2.
Full decision text continues on ProtestIntel...