Massaro Company; Poerio Inc., B-280772.2; B-280772.3,
Case: B-280772.2
Agency:
Protester: Massaro Company; Poerio Inc., B
Date: 1998-12-04
Sustained
Massaro Company; Poerio Inc., B-280772.2; B-280772.3,
BNUMBER: B-280772.2; B-280772.3
DATE: December 4, 1998
TITLE: Massaro Company; Poerio Inc., B-280772.2; B-280772.3,
December 4, 1998
**********************************************************************
Matter of:Massaro Company; Poerio Inc.
File: B-280772.2; B-280772.3
Date:December 4, 1998
Joseph A. Massaro, Jr., Esq., for Massaro Company; and Keith L. Baker,
Esq., and Jeffrey E. Weinstein, Esq., Eckert Seamans Cherin & Mellott,
for Poerio Inc., the protesters.
Kenneth B. MacKenzie, Esq., and Charlma Quarles, Esq., Department of
Veterans Affairs, for the agency.
Susan K. McAuliffe, Esq., and Christine S. Melody, Esq., Office of the
General Counsel, GAO, participated in the preparation of the decision.
DIGEST
Agency did not have a compelling reason to cancel solicitation after
bid opening based upon allegedly ambiguous pricing requirements, where
the solicitation, when read as a whole, is susceptible to only one
reasonable interpretation regarding how bidders were to structure
their bids.
DECISION
Massaro Company and Poerio Inc. protest the cancellation after bid
opening of invitation for bids (IFB) No. 9810 A/E, issued by the
Department of Veterans Affairs (VA) for the environmental improvement
of three inpatient units at the VA Medical Center, Pittsburgh,
Pennsylvania. The protesters contend that, contrary to the agency's
stated reason for canceling the IFB, the solicitation's pricing terms
were not ambiguous; the protesters seek reinstatement of the canceled
IFB.
We sustain Poerio's protest and deny Massaro's protest for lack of
prejudice.
The IFB, issued on June 1, 1998, required bidders to provide prices
("figures") for two bid items (items I and II, described below) and
three alternates (described as minor additions or deletions to the
IFB's performance requirements); a unit price for mine grouting also
was required. The IFB provided, at sec. 01010, para. 1.2.A., the following
descriptions:
STATEMENT OF BID ITEM(S)
ITEM I, GENERAL CONSTRUCTION: Work includes general new
construction, alterations, walks, grading, paving, drainage,
mechanical and electrical work, elevators, necessary removal of
existing structures and construction and certain other items.
ITEM II, ASBESTOS ABATEMENT: Work includes abatement of asbestos
in the area of the work as well as in other selected areas,
including the work described in ALTERNATE 2 below.[[1]]
Amendment No. 2 to the IFB, issued on July 1, included the following
clarification:
Although the VA has asked for the price of the Asbestos Abatement
work to be listed separately (ITEM II - ASBESTOS ABATEMENT . . .
) on the bid form, all asbestos abatement work is included in a
single prime contract that will be the responsibility of the
General Contractor.
Nine bids were received at bid opening on July 15. Poerio's total bid
of $11,401,500 ($10,687,000 for bid item I, plus $714,500 for bid item
II) was the apparent low bid received. Massaro's total bid,
calculated by the agency to be $11,586,000 ($10,886,000 for bid item
I, plus $700,000 for bid item II), was the apparent second low bid
received.
After bid opening, the president of Massaro notified the contracting
officer that the firm's item I (general construction) price
represented Massaro's total bid price, since it included Massaro's
item II (asbestos abatement) price. Massaro explained to the
contracting officer that, prior to bid opening, the firm was unclear
about how to price items I and II--i.e., whether the item I and II
prices were to represent different portions of the overall work, so
that the bidder's total price for all work under the solicitation was
the sum of the prices bid for items I and II; or whether the price for
item I should represent the bid for all work included under the
solicitation, with the price provided for item II merely identifying
the portion of the item I price related to asbestos abatement.
According to Massaro, it asked an individual at the office of the VA's
architect for the project for direction. Massaro states that the
individual instructed Massaro to structure its bid, as it ultimately
did, by including the price for the item II work in the firm's item I
price. Massaro then listed its break-out price for the asbestos
abatement work as its item II price.[2]
The contracting officer requested work papers from Massaro to support
the firm's claim as to its intended total bid price. Massaro
submitted undated work papers, allegedly produced by computer on the
day of bid opening.
Full decision text continues on ProtestIntel...