Eastern Technical Enterprises, Inc., B-281319; B-281320,
Case: B-281319
Agency:
Protester: Eastern Technical Enterprises, Inc., B
Date: 1999-01-22
Denied
Eastern Technical Enterprises, Inc., B-281319; B-281320,
BNUMBER: B-281319; B-281320
DATE: January 22, 1999
TITLE: Eastern Technical Enterprises, Inc., B-281319; B-281320,
January 22, 1999
**********************************************************************
Matter of:Eastern Technical Enterprises, Inc.
File: B-281319; B-281320
Date:January 22, 1999
Michael J. Gardner, Esq., Clark & Stant, for the protester.
Kenneth A. Lechter, Esq., Department of Commerce, for the agency.
Susan K. McAuliffe, Esq., and Christine S. Melody, Esq., Office of the
General Counsel, GAO, participated in the preparation of the decision.
DIGEST
Cancellation of an invitation for bids after bid opening is proper
where solicitation does not reflect changed requirements in work and
award under the solicitation would not serve the government's actual
needs.
DECISION
Eastern Technical Enterprises, Inc. protests the cancellation of
invitation for bids (IFB) No. 51-EANA-8-00076, issued by the
Department of Commerce, National Oceanic and Atmospheric
Administration (NOAA), for the drydocking and repair of NOAA Ship
ALBATROSS IV. The protester's challenge is based upon the terms of
the agency's resolicitation of the procurement through the issuance of
request for proposals (RFP) No. 52-EANA-9-00002. Eastern contends
that the RFP did not contain sufficient changes in requirements to
support the agency's cancellation of the IFB.
We deny the protest.
The IFB was issued on July 22, 1998 to 16 firms. Three bids were
received by the September 8 bid opening. Eastern's bid of $599,469
was the apparent low bid received; bids of $848,682 and $1,097,402
were received from two other firms. On September 22, the agency
canceled the IFB due to changes in its requirements. The protester
received notice of the cancellation on October 6. On the same day,
Eastern received the RFP, the agency's resolicitation of the canceled
requirement. After comparing the two solicitations' requirements,
Eastern filed its current protest, contending that the changes in
requirements were minor and do not support the agency's cancellation
of the IFB.[1]
Preservation of the integrity of the competitive bidding system
dictates that after bids have been opened, award must be made to that
responsible bidder which submitted the lowest responsive bid, unless
there is a compelling reason to reject all bids and cancel the IFB.
Federal Acquisition Regulation (FAR) sec. 14.404-1(a)(1); Zwick Energy
Research Org., Inc., B-237520.3, Jan. 25, 1991, 91-1 CPD para. 72 at 2-3.
However, an IFB may be canceled after bid opening, and all bids
rejected, where award under the IFB would not serve the government's
actual needs, and the specifications therefore need to be revised.
FAR sec. 14.404-1(c)(1), (2); I.T.S. Corp., B-243223, July 15, 1991, 91-2
CPD para. 55 at 3-4.
We conclude that the cancellation here was proper. As discussed
below, the record shows that the agency's needs have materially
changed since the issuance of the IFB, as evidenced by the
significantly relaxed requirements contained in the RFP.[2]
The agency cites several examples of changes it believes are
sufficiently significant to justify the cancellation. For example, in
basic item No. 1 of the IFB's performance requirements, regarding
drydocking and routine drydock work, the agency has deleted two
requirements: (1) the requirement that the single section floating
drydock be capable of leveling the ship within +/-2 minutes of arc
with reference to the horizontal gravity plane (IFB Detail
Specifications (DS) sec. 3.1.3(c)); and (2) the requirement that the ship
be drydocked on 60-inch minimum height keel blocks (Id. sec. 3.1.3(b)).
The Lead Port Engineer explains that these two requirements--which
pertain to certain ship transducer and underwater body work not
required under the IFB--were mistakenly included in the IFB, and that
they exceed the agency's actual drydocking needs. Specifically, he
explains the restrictive nature of the unnecessary requirements, and
the materiality of their deletion as follows:
Eliminating the tight-tolerance ship leveling requirement
provides contractors with the option of performing the work in a
graving dock or marine railway instead of only in a single
section floating drydock. Eliminating the 60-inch minimum keel
block height requirement allows the ship to be drydocked on more
common 48-inch block heights, and in facilities with limited
draft capabilities, further increasing competition. These
requirements were needed when the ship had transducer work
scheduled in conjunction with underwater body work in drydock.
Transducer work was not scheduled for this drydock and repair
period and the requirements should not have been included in the
specification.
Declaration of James B.
Full decision text continues on ProtestIntel...