Bulova Technologies LLC, B-281384; B-281384.2, February 3,
Case: B-281384
Agency:
Protester: Bulova Technologies LLC, B
Date: 1999-02-03
Denied
Bulova Technologies LLC, B-281384; B-281384.2, February 3,
BNUMBER: B-281384; B-281384.2
DATE: February 3, 1999
TITLE: Bulova Technologies LLC, B-281384; B-281384.2, February 3,
1999
**********************************************************************
DOCUMENT FOR PUBLIC RELEASE
The decision issued on the date below was subject to a GAO Protective
Order. This redacted version has been approved for public release.
Matter of:Bulova Technologies LLC
File:B-281384; B-281384.2
Date:February 3, 1999
Glenn A. Rowley, Esq., John E. McCarthy, Jr., Esq., and Donald E.
Sovie, Esq., Crowell & Moring, for the protester.
Larisa A. Trainor, Esq., Anne B. Perry, Esq., and Louis D. Victorino,
Esq., Fried, Frank, Harris, Shriver & Jacobson, an intervenor.
Larry Brady, Esq., Gerald T. Williams, Esq., and Maj. Cynthia M.
Mabry, U.S. Army Materiel Command, for the agency.
Marie Penny Ahearn, Esq., and John M. Melody, Esq., Office of the
General Counsel, GAO, participated in the preparation of the decision.
DIGEST
1. Allegation that protester would have been able to eliminate
certain deficiencies in the portion of its proposal related to a
certain item, had the agency made predecessor contract information
available, is untimely where first raised after closing time for
receipt of proposals and protester knew that the item had been used
under prior contract (and actually requested that the item be provided
as government-furnished equipment), but neither requested information
about the item, nor protested its omission from the solicitation prior
to the closing time.
2. Protest that agency improperly considered offerors' experience in
manufacturing specific item being acquired is denied where evaluation
factors encompassed consideration of such experience.
3. Protest that evaluation improperly was based on unstated
criteria--methodology to mitigate component obsolescence of a specific
component--is denied where, contrary to protester's position, record
indicates that evaluation was conducted on basis of general
methodology to mitigate component obsolescence, as provided for in
solicitation, and protester failed to present a plan in this area.
4. Protest that agency improperly evaluated protester's price
assumption--that component parts will function properly when
manufactured to technical data package and assembled--as inconsistent
with solicitation is denied, where solicitation specifically provided
that contractor was not to assume that all possible combinations of
tolerances and fits permitted by specifications/drawings would
consistently satisfy test requirements.
5. Where solicitation advised offerors that government intended to
make award on basis of intitial proposals, contracting agency was not
obligated to conduct discussions concerning protester's proposal,
which was rated marginal with significant weaknesses based on
omissions/informational deficiencies.
DECISION
Bulova Technologies LLC protests the award of a contract to KDI
Precision Products, Inc. under request for proposals (RFP) No.
DAAE30-98-R-0310, issued by the Department of the Army for production,
testing, load, assembly, pack, and delivery of M734A1 fuzes used in
120mm mortar systems.[1] The protester challenges the evaluation and
award on several grounds.
We deny the protest.
The RFP, which limited competition to small businesses, provided for
award of a fixed-price contract on a best value basis, applying the
following four evaluation factors, in descending order of importance:
(1) quality, (2) cost, (3) management, and (4) past performance. In
the actual evaluation, quality was weighted at 50 percent, cost at 25
percent, management at 15 percent, and past performance at 10 percent.
The quality factor included three subfactors--manufacturing process,
technical capabilities and facilities/capital equipment. The
management factor included two subfactors--program management and
configuration management. The RFP provided that quality and
management were to be assigned color ratings of blue, green, yellow,
or red and assessed for proposal risk using the ratings of low,
moderate, and high.[2] Past performance was to be evaluated using the
same adjectival risk ratings. RFP sec. M.1, M.3-M.6, at 84-92. Cost
was to be evaluated by adding the price for the basic year (first
article and production quantity) to the total of all evaluated prices
for all option years. The solicitation provided that the "Government
intends to award without discussions" and, therefore, "[e]ach initial
offer should contain the offeror's best terms." RFP sec. M.2, at 85.
The statement of work consisted of a CD-ROM technical data package
(TDP) with requirements and drawings which were described as
"defin[ing] the effort required" and were to be used "as the approved
Product Baseline documentation . . .
Full decision text continues on ProtestIntel...