L-3 Communications Corporation, Ocean Systems Division, B-
Case: B-281784.3
Agency:
Protester: L
Date: 1999-04-26
Sustained In Part, Denied In Part
L-3 Communications Corporation, Ocean Systems Division, B-
BNUMBER: B-281784.3; B-281784.4
DATE: April 26, 1999
TITLE: L-3 Communications Corporation, Ocean Systems Division, B-
281784.3; B-281784.4, April 26, 1999
**********************************************************************
DOCUMENT FOR PUBLIC RELEASE
The decision issued on the date below was subject to a GAO Protective
Order. This redacted version has been approved for public release.
Matter of:L-3 Communications Corporation, Ocean Systems Division
File: B-281784.3; B-281784.4
Date:April 26, 1999
John H. Horne, Esq., Steffanie F. Walke, Esq., Carl A. Gebo, Esq.,
David C. Hammond, Esq., and Mary Baroody Lowe, Esq., Powell,
Goldstein, Frazer & Murphy, for the protester.
Thomas L. McGovern III, Esq., Michael F. Mason, Esq., Robert J.
Kenney, Jr., Esq., and S. Gregg Kunzi, Esq., Hogan & Hartson; and
Bucky P. Mansuy, Esq., for Lockheed Martin Integrated Systems, Inc.,
the intervenor.
Josie C. Serracin, Esq., Michael Glennon, Esq., Eileen White, Esq.,
Kelly Swartz, Esq., and Trina Alexander, Esq., Department of the Navy,
Naval Sea Systems Command, for the agency.
Susan K. McAuliffe, Esq., and Christine S. Melody, Esq., Office of the
General Counsel, GAO, participated in the preparation of the decision.
DIGEST
1. Protest of agency's upward adjustment to protester's cost proposal
in evaluation for cost realism is sustained where agency improperly
relied on an unaudited summary of indirect rate data obtained from the
Defense Contract Audit Agency (DCAA) which was rescinded by the
protester as unauthorized and invalid shortly after submission to
DCAA. Although DCAA failed to notify the contracting agency, prior to
award, of the rescission of those rates, agency's use of the rescinded
rates nevertheless was improper because the agency made no attempt at
verifying their reliability, despite the fact that the rates were
unsupported, summary in nature, and not reviewed by DCAA. Further,
even after the contracting agency had actual knowledge of the
rescission of those rates, it improperly continued to rely on those
rates in conducting post-award re-analysis of the protester's indirect
rates.
2. Agency's disallowance of protester's proposed uncompensated
overtime (UCOT) is unobjectionable where contemporaneous evaluation
record adequately documents agency's legitimate concerns regarding the
protester's proposal's lack of detail about the firm's successful use
of UCOT on prior contracts, and the UCOT proposal's potential adverse
effects on employee morale and retention, and contract performance.
DECISION
L-3 Communications Corporation, Ocean Systems Division, protests the
award of a contract to Lockheed Martin Integrated Systems, Inc. under
request for proposals (RFP) No. N00024-98-R-6207, issued by the
Department of the Navy, Naval Sea Systems Command (NAVSEA), for the
design and production of Omnibus Towed Array Systems. L-3 contends
that the agency improperly adjusted its proposed costs upward in
evaluating the firm's proposal for cost realism; specifically, the
protester challenges as unreasonable the agency's upward adjustment of
L-3's proposed indirect rates on the basis of alleged erroneous and
invalid L-3 rate data obtained from the Defense Contract Audit Agency
(DCAA), failure to accept L-3's "fixed price" subcontractor costs as
proposed, and disallowance of L-3's proposed uncompensated overtime.
Additionally, L-3 protests the propriety of the agency's best value
determination on the ground that selection of an offeror that
submitted the lower-cost, lower technically rated proposal was
unreasonable and inconsistent with the RFP's evaluation scheme, which
provided that the technical considerations were to be more important
than cost.[1]
We sustain the protest in part, and deny it in part.[2]
BACKGROUND
The solicitation
The RFP, issued on April 16, 1998, contemplated the award of a
cost-plus-fixed-fee, level-of-effort engineering services contract,
with options for cost-plus-incentive-fee low rate initial production
(LRIP) and an ordering provision for fixed-price full rate production
of Navy towed systems.[3] Offerors were to base their proposals on
four sample tasks considered indicative of the type of work required
under the contract. Section M of the RFP set forth the evaluation
factors for award, where the technical proposal was "more important"
than the cost proposal.[4] RFP sec. M, para. 2.1, at 222. Offerors were
advised of the agency's willingness to pay a cost premium for a
technically superior proposal offering the best value to the
government. RFP sec. M, para. 3.3, at 230.
Sections L and M of the RFP provided instructions regarding the
preparation and submission of cost proposals. Offerors were notified
that the agency would evaluate proposals for reasonableness and
realism. RFP sec. M, para. 2.7.1, at 225.
Full decision text continues on ProtestIntel...