Tony's Landscaping, Inc., B-283794, November 23, 1999
Case: B-283794
Agency:
Protester: Tony's Landscaping, Inc., B
Date: 1999-11-23
Denied
B-283794
Nov 23, 1999
Jump To
VIEW DECISION
RELATED PAGES
GAO CONTACTS
Highlights
DIGEST Agency was not required to conduct discussions but could have a limited exchange with proposed awardee pursuant to Federal Acquisition Regulation Sec. 15.306(a)(2) for the purpose of clarifying and correcting proposed awardee's pricing error. Where the existence of the clerical error and the price actually intended was clear from the proposal. Offerors were requested to provide fixed prices under section I of the RFP under four service categories (for example. The pricing blanks for these CLINS were marked with an asterisk. Whose pricing blanks were marked with a double asterisk. 000 estimated price per year was provided for evaluation purposes. Section I also included the following notation: NOTE: Items/Columns with an * notation are to be completed by offerors.
View Decision
Matter of: Tony's Landscaping, Inc. File: B-283794 Date: November 23, 1999
DIGEST
Attorneys
DECISION
Tony's Landscaping, Inc. protests the proposed award of a contract to Miranda's Landscaping, Inc. under request for proposals (RFP) No. F04684-99-R-0006, issued by the Department of the Air Force for grounds maintenance at Vandenberg Air Force Base, California. The protester complains that the Air Force improperly allowed Miranda's Landscaping to correct its proposal price.
We deny the protest.
The RFP, issued as a competitive, section 8(a) set-aside, sought proposals to perform a variety of grounds maintenance services for a base year with 4 option years. For each contract year, offerors were requested to provide fixed prices under section I of the RFP under four service categories (for example, grounds maintenance (contract line item (CLIN) 0001), tree line maintenance (CLIN 0002), roadside maintenance and herbicide application (CLIN 0003), and herbicide/sterilant application (CLIN 0004)). RFP at 3-12. The pricing blanks for these CLINS were marked with an asterisk. Section I included two other CLINS for each contract year: CLIN 0005, task orders, whose pricing blanks were marked with a double asterisk, and CLIN 0006, a cost-reimbursable item for which a $60,000 estimated price per year was provided for evaluation purposes. Section I also included the following notation:
NOTE: Items/Columns with an * notation are to be completed by offerors. Item with ** notation is funded by individual Task Orders.
Instructions as to how task orders would be issued and priced were provided in appendix G of the RFP. In this regard, the appendix requested, for each contract year, offerors' burdened labor rates for specified labor categories and provided for each labor category an estimated number of hours against which the proposed labor rate would be multiplied to calculate the offerors' evaluated task order costs. RFP app. G, at 16-21.
In addition to proposed pricing, the RFP requested that each offeror complete a past performance questionnaire and provide an oral presentation that would describe the offeror's staffing and organization, discuss the offeror's understanding of CLINs 0001 through 0004, and describe the offeror's methodology and approach to implementing a quality system to satisfy the contract requirements. RFP at 18-19.
The RFP provided for award without discussions. RFP at 17 (incorporating by reference Federal Acquisition Regulation (FAR) Sec. 52.212-1). Offerors were informed that for those proposals that were determined to be technically acceptable the Air Force would trade off offerors' past performance risk and evaluated price to determine which offer was the most advantageous to the government. RFP at 21. In this regard, price and past performance risk were stated to be of equal importance. Offeror were informed that the agency would add the fixed prices for all contract years from section I to the estimated costs from section G to determine the lowest total evaluated price. RFP at 22.
Five proposals were received in response to the RFP. Contracting Officer's Statement at 1. Three proposals, including those of the protester and the proposed awardee, were determined to be technically acceptable. Only the protester's and proposed awardee's proposals were considered for award because the third offeror's price was considered to be too high. The agency then compared the proposed awardee's exceptional past performance risk rating and $9,144,185 evaluated price to the protester's very good past performance risk rating and $8,918,249 evaluated price. The Air Force initially concluded that the protester's proposal reflected the best value to the government, given its apparent lower evaluated price, and the offerors were so notified. Id.
Prior to award being made, Miranda's Landscaping complained to the contracting officer that its proposed price was actually lower than the protester's. Id. at 2.
Full decision text continues on ProtestIntel...