Spacesaver Systems, Inc., B-284924; B-284924.2, June 20, 2000
Case: B-284924
Agency:
Protester: Spacesaver Systems, Inc., B
Date: 2000-06-20
Denied
Spacesaver Systems, Inc., B-284924; B-284924.2, June 20, 2000
TITLE: Spacesaver Systems, Inc., B-284924; B-284924.2, June 20, 2000
BNUMBER: B-284924; B-284924.2
DATE: June 20, 2000
**********************************************************************
Spacesaver Systems, Inc., B-284924; B-284924.2, June 20, 2000
Decision
Matter of: Spacesaver Systems, Inc.
File: B-284924; B-284924.2
Date: June 20, 2000
William J. Spriggs, Esq., Spriggs & Hollingsworth, for the protester.
Jeffrey C. Morhardt, Esq., Department of Education, for the agency.
Scott H. Riback, Esq., and John M. Melody, Esq., Office of the General
Counsel, GAO, participated in the preparation of the decision.
DIGEST
Protest that agency improperly performed cost/technical tradeoff under a
best value acquisition approach for a Federal Supply Schedule (FSS) purchase
without advising vendors of this evaluation method, is denied where record
shows that, in fact, agency did not conduct a best value evaluation or
perform a tradeoff; rather, agency rejected protester's lower-priced product
as unacceptable for failing to meet delivery requirements, and made award to
the FSS vendor offering to meet all requirements at the lowest overall cost
to the government.
DECISION
Spacesaver Systems, Inc. protests the Department of Education's (DOE) award
of two delivery orders to Capitol Office Systems, Inc. under that firm's
Federal Supply Schedule (FSS) contract for high density filing systems.
Spacesaver alleges that the agency improperly failed to make award to the
low-priced, technically acceptable firm, and also failed to afford it an
opportunity to respond to a revision to the agency's requirements.
We deny the protest.
The agency was interested in acquiring approximately 47,000 linear inches of
high density filing systems in connection with the move of the National
Center for Education Statistics (NCES) from one location in Washington, D.C.
to another. The agency decided to make its purchase from the FSS and
contacted five vendors, including the protester, that held current FSS
contracts for the filing systems. In this connection, the record shows that
on February 29, 2000 the agency provided the vendors (by facsimile) a
document entitled "Scope of Work" (SOW), which requested information from
the vendors regarding the requirement. [1] Of importance for purposes of the
protest, the SOW stated that the agency required the filing systems to be
installed by March 30 and April 6 (the two dates relate to systems to be
installed on two different floors of the NCES's new offices), and required
offerors to provide information regarding their proposed configurations by
March 3. SOW at 1. The SOW also specifically asked offerors to identify
separate costs associated with items that were not covered under their FSS
contracts. Id.
In response to the agency's request, Spacesaver submitted pricing and
configuration information. In the March 3 cover letter accompanying its
submission, Spacesaver advised the agency as follows:
In order to meet your deadlines . . . we are quoting all Quickship products.
These products are not available on [our FSS] contract at this time. . . .
In order for us to meet [the agency's delivery requirements], we will need
to have an order no later than Monday, March 6th. . . . For every day the
order is delayed after March 6 delivery and installation time will increase
by two days.
The only product we cannot deliver in time will be the full height locking
doors for the mobile systems on the 9th [floor]. These will be installed 7
weeks from the time of order.
Our standard products are available on [FSS] contract and we can offer them
to you on [FSS] contract, but they take 6 weeks to ship, plus installation
time.
(The record also shows that Spacesaver's submission to the agency was
unclear regarding whether its terms included the filing systems for one of
the rooms in question. Agency Report, Apr. 14, 2000, at 3.)
On March 9, subsequent to receiving information from the vendors, the agency
issued a document entitled "Modification to Scope of Work." In this
document, the agency advised vendors that the anticipated award date had
slipped a few days, that the agency now anticipated awarding the purchase
order on March 10, and that DOE needed revised information regarding the
vendors' installation schedules. This document was not provided to the
protester, apparently because of the statement in Spacesaver's original
submission that, even with its Quickship line of products (which were not
available under Spacesaver's FSS contract, and therefore could not properly
have been ordered by the agency), installation would be delayed an
additional 2 days for every day the order was delayed after March 6.
Full decision text continues on ProtestIntel...