Ktech
Case: B-285330
Agency: Department of Defense : Defense Threat Reduction Agency
Protester: Ktech
Date: 2000-08-17
Sustained
Ktech
TITLE: Ktech
Corporation, B-285330;
B-285330.2, August 17,
2000
BNUMBER: B-285330;
B-285330.2
DATE: August 17,
2000
**********************************************************************
DOCUMENT FOR PUBLIC RELEASE
The decision issued on the date below was subject to a GAO Protective
Order. This redacted version has been approved for public release.
Decision
Matter of: Ktech Corporation
File: B-285330; B-285330.2
Date: August 17, 2000
Robert S. Gardner, Esq., for the protester.
Thomas F. Burke, Esq., McKenna & Cuneo, for Maxwell Technologies, an
intervenor.
David C. Rickard, Esq., Defense Threat Reduction Agency, for the agency.
Scott H. Riback, Esq., and John M. Melody, Esq., Office of the General
Counsel, GAO, participated in the preparation of the decision.
DIGEST
Protest that awardee's subcontractor has impermissible conflict of interest
is sustained where record shows that agency did not consider possibility
that subcontractor may have improperly obtained, through performance of
earlier government contract, information confidential to protester and used
it to enhance capabilities made available to awardee, and agency did not
analyze possible conflicting roles that subcontractor may be required to
perform under protested contract and subcontractor's other government work.
DECISION
Ktech Corporation protests the award of a contract to Maxwell Technologies
under request for proposals (RFP) No. DTRA01-00-R-0009, issued by the
Defense Threat Reduction Agency (DTRA) for the operation of a magnetic flyer
plate facility, and the performance of certain tests within the facility.
Ktech asserts that the awardee has an impermissible organizational conflict
of interest, that the agency made its award decision on a basis other than
that announced during the acquisition, and that the agency failed to conduct
meaningful discussions with it.
We sustain the protest.
BACKGROUND
The solicitation contemplated the award of a cost-reimbursement contract to
perform various services in connection with the operation of the agency's
magnetic flyer plate (mag flyer) facility in Albuquerque, New Mexico. This
facility is used for testing reentry bodies (RBs)[1] to ensure that they are
sufficiently 'hardened' against forces and effects that might occur in a
hostile environment. RFP Statement of Work (SOW) at 1. The work to be
performed under the RFP is divided into three phases. Under phase 1, the
agency's mag flyer facility is to be brought up to full operational status
(the facility had been previously 'mothballed'). Included under phase 1 are
the design, manufacture, integration testing and evaluation of all equipment
necessary to conduct the tests. Id. Under phase 2 (an option under the
contract), the contractor is required to conduct calibration of the
equipment, and to execute full scale testing on two RBs. Id. The agency
contemplated that the phase 1 work would take approximately 12 months and
that the phase 2 work would take approximately 6 months (4 months for
testing and 2 months for reporting the data). Commerce Business Daily, Nov.
23, 1999. Testimony at the hearing that our Office conducted in this matter
shows that the agency originally intended to obtain the test data by July 1,
2001. Hearing Transcript (Tr.) at 75. Under phase 3 (also optional), the
contractor is required to provide support that will keep the facility safe
and secure for a period of 1 year, and to provide the government with cost
estimates for performing any additional tests approved by the agency. SOW
at 6.
Technical considerations were more important than price, price was more
important than past performance considerations, and technical and past
performance considerations, when combined, were significantly more important
than price. RFP at 46-47. Award was to be made on a best value basis. Id.
The agency received three initial proposals, two of which (Maxwell's and
Ktech's) were included in the competitive range. The agency engaged in
discussions with both firms and obtained final proposal revisions (FPR).
[deleted]. Memorandum from the Source Selection Evaluation Board (SSEB) to
the Contracting Officer, Source Selection Recommendation at 1-2 (Mar. 10,
2000). [deleted]. Id. at 4.
Subsequent to the March 10 recommendation, members of the source selection
evaluation board (SSEB) met with other agency officials [deleted]. Tr. at
76-77, 172, 181-84, 302-08. On the basis of these meetings, the SSEB
members prepared a second memorandum dated March 30 [deleted]. The agency
proceeded with the award and, after a debriefing, this protest followed.
ORGANIZATIONAL CONFLICT OF INTEREST (OCI)
Ktech asserts that award to Maxwell was improper due to an OCI arising out
of the activities of one of its subcontractors, ITT Industries.
Full decision text continues on ProtestIntel...