J W Holding Group & Associates, Inc., B-285882.3; B-285882.6, July 2, 2001
Case: B-285882.3
Agency:
Protester: J W Holding Group & Associates, Inc., B
Date: 2001-07-02
Denied
J W Holding Group & Associates, Inc., B-285882.3; B-285882.6, July 2, 2001
TITLE: J W Holding Group & Associates, Inc., B-285882.3; B-285882.6, July 2, 2001
BNUMBER: B-285882.3; B-285882.6
DATE: July 2, 2001
**********************************************************************
J W Holding Group & Associates, Inc., B-285882.3; B-285882.6, July 2, 2001
DOCUMENT FOR PUBLIC RELEASE
The decision issued on the date below was subject to a GAO Protective
Order. This redacted version has been approved for public release.
Decision
Matter of: J W Holding Group & Associates, Inc.
File: B-285882.3; B-285882.6
Date: July 2, 2001
Daniel Koch, Esq., Paley, Rothman, Goldstein, Rosenberg & Cooper, for the
protester.
Mathew S. Perlman, Esq., Richard J. Webber, Esq., and Natalie S. Walters,
Esq., Arent Fox, for Sodexho Marriott Management, an intervenor.
Julius Rothlein, Esq., Headquarters U.S. Marine Corps, for the agency.
David A. Ashen, Esq., and John M. Melody, Esq., Office of the General
Counsel, GAO, participated in the preparation of the decision.
DIGEST
Regulation requiring source selection authority (SSA) to exercise
*independent judgment* does not preclude SSA from acting as head of the
price evaluation team.
DECISION
J.W. Holding Group & Associates, Inc. (JWH) protests the U.S. Marine
Corps's (USMC) award of a contract to Sodexho Marriott Management (SMM)
under request for proposals (RFP) No. M00027‑00‑R‑0002,
for regional garrison food service on the West Coast. The protester
challenges the conduct of the evaluation.
We deny the protest.
The RFP provided for award of a primarily fixed-price incentive contract
for a base period of 5 years, with 3 option years, to provide regional
garrison food service at 23 messhalls on the West Coast. Award was to be
made on a best-value basis, with proposals to be evaluated under four
criteria: price, integrated organization and management, small business
subcontracting plan, and past performance. Price was the most important
criterion and was equal in importance to the other criteria combined.
Four offerors submitted proposals. SMM's, JWH's and a third offeror's
(Eurest Support Services (ESS)) proposals were included in the competitive
range. After conducting written and oral discussions, USMC requested
final proposal revisions (FPR). The FPR evaluation results were as
follows:
+------------------------------------------------------------------------+
| |JWH |ESS |SMM |
|---------------------------------------+----------+----------+----------|
|Meal Service (Fixed Price Incentive) | | | |
|---------------------------------------+----------+----------+----------|
| Target Cost per Meal |$[DELETED]|$[DELETED]|$[DELETED]|
| Target Price per Meal | | | |
|---------------------------------------+----------+----------+----------|
| Total Target Price |$[DELETED]|$[DELETED]|$[DELETED]|
|---------------------------------------+----------+----------+----------|
| Share Ratio (USMC/ |[DELETED] |[DELETED] |[DELETED] |
| Contractor) | | | |
|---------------------------------------+----------+----------+----------|
| Ceiling Price Per Meal |$[DELETED]|$[DELETED]|$[DELETED]|
|---------------------------------------+----------+----------+----------|
|Meals per Labor Hour |[DELETED] |[DELETED] |[DELETED] |
|---------------------------------------+----------+----------+----------|
|Hour Maintenance (Fixed Price) |$[DELETED]|$[DELETED]|$[DELETED]|
|---------------------------------------+----------+----------+----------|
|Time & Materials (T&M) |$[DELETED]|$[DELETED]|$[DELETED]|
|---------------------------------------+----------+----------+----------|
|Total Price (Target Price+ |$[DELETED]|$[DELETED]|$[DELETED]|
|Maintenance+T&M) | | | |
|---------------------------------------+----------+----------+----------|
|Total Price (Ceiling Price+ |$[DELETED]|$[DELETED]|$[DELETED]|
|Maintenance+T&M) | | | |
|---------------------------------------+----------+----------+----------|
|Risk | | | |
| Proposal |Moderate |Low |Low |
| Performance |Moderate |Moderate |Low |
|---------------------------------------+----------+-...