McDonald Construction Services, Inc., B-285980; B-285980.2, October 25, 2000
Case: B-285980
Agency:
Protester: McDonald Construction Services, Inc., B
Date: 2000-10-25
Denied
McDonald Construction Services, Inc., B-285980; B-285980.2, October 25, 2000
TITLE: McDonald Construction Services, Inc., B-285980; B-285980.2, October 25, 2000
BNUMBER: B-285980; B-285980.2
DATE: October 25, 2000
**********************************************************************
McDonald Construction Services, Inc., B-285980; B-285980.2, October 25, 2000
Decision
Matter of: McDonald Construction Services, Inc.
File: B-285980; B-285980.2
Date: October 25, 2000
Thomas E. Abernathy IV, Esq., Smith, Currie & Hancock, for the protester.
Robert A. Emmanuel, Esq., Emmanuel, Sheppard & Condon, for Greenhut
Construction Services, Inc., the intervenor.
Thomas W. Burt, Esq., and Larry E. Beall, Esq., U.S. Army Corps of
Engineers, for the agency.
Aldo A. Benejam, Esq., and Christine S. Melody, Esq., Office of the General
Counsel, GAO, participated in the preparation of the decision.
DIGEST
Protester's contention that the agency unreasonably evaluated its proposal
because it was downgraded under three separate evaluation areas for the same
deficiency is denied, where the record shows that the agency evaluated the
protester's proposal in accordance with the criteria announced in the
solicitation, the criteria assessed separate aspects of the proposals, and
the deficiencies noted reasonably related to all three evaluation areas at
issue.
DECISION
McDonald Construction Services, Inc. protests the award of a contract to
Greenhut Construction Services, Inc. under request for proposals (RFP) No.
DACA01-00-R-0009, issued by the U.S. Army Corps of Engineers for the
construction of a hospital central energy plant at Eglin Air Force Base,
Florida. McDonald challenges the evaluation of its proposal and contends
that the agency improperly conducted discussions with the awardee, while it
failed to conduct similar discussions with McDonald.
We deny the protest.
BACKGROUND
The RFP, issued on March 1, 2000, contemplated the award of a fixed-price
contract for the construction of the required plant, which generally
consists of a steel frame building with slab on grade floor and concrete
foundation. The building is to be a free-standing central energy facility
housing the existing chiller and boiler assets which will be relocated from
the main hospital to the new plant. Offerors were required to submit fixed
prices for the basic requirement, for each of four option items, and a total
price. Offerors were instructed to submit proposals in two separate
volumes--performance capability (volume I), and "pro forma" requirements
(volume II). The RFP contained detailed instructions on the type of
information required to be included in each volume.
Section 00120 of the RFP explained that a source selection evaluation board
(SSEB) would evaluate volume I of the proposals in the areas listed below.
Volume II, which was to include such items as contractor representations and
certifications, bonds, standard form 1442, the schedule, and subcontracting
plan, was to be evaluated separately on a "go or no-go" basis; the financial
statement, which was also to be included in volume II, was not to be
evaluated. Price was not to be numerically scored but was to be evaluated
for fairness and reasonableness. The RFP stated that the technical area
(i.e., performance capability) and price were equal in importance. In
addition, the RFP stated that the government may make award without
discussions, and cautioned offerors to provide their best terms in the
initial proposals. Award was to be made to the offeror whose proposal was
deemed most advantageous to the government.
The RFP listed the following subfactors for evaluating volume I and their
relative importance (maximum point values for each subfactor shown were not
provided in the RFP but were set out in the instructions provided to the
SSEB).
Factor/Subfactor Value
Vol. I--Perf.
Capability
Organization 200
Specific Personnel 125
Specialized Experience 200
on Similar Type of
Work
Preliminary Quality 100
Control Plans
Preliminary Project 60
Schedules
Past Perf. on 40
Utilization of Small
Bus. Concerns
Safety Program 75
Total Points 800
Nine firms submitted proposals by the time set on June 8 for receipt of
initial proposals, ranging in total price from McDonald's low price of
$5,565,007 to $7,602,895; Greenhut submitted the second lowest total price.
As for technical scores, the protester's proposal was ranked seventh while
Greenhut's proposal was ranked first.
Full decision text continues on ProtestIntel...