Goode Construction, Inc.--Protest and Costs, B-288655.4; B-288655.5; B-288655.6, January 28, 2002
Case: B-288655.4
Agency:
Protester: Goode Construction, Inc.
Date: 2002-01-28
Denied
Goode Construction, Inc.--Protest and Costs, B-288655.4; B-288655.5; B-288655.6, January 28, 2002
TITLE: Goode Construction, Inc.--Protest and Costs, B-288655.4; B-288655.5; B-288655.6, January 28, 2002
BNUMBER: B-288655.4; B-288655.5; B-288655.6
DATE: January 28, 2002
**********************************************************************
Decision
Matter of: Goode Construction, Inc.--Protest and Costs
File: B-288655.4; B-288655.5; B-288655.6
Date: January 28, 2002
Robert E. Korroch, Esq., Williams Mullen Clark & Dobbins, for the protester.
Keith A. Moore-Erickson, Esq., United States Coast Guard, for the agency.
Mary G. Curcio, Esq., and John M. Melody, Esq., Office of the General
Counsel, GAO, participated in the preparation of the decision.
DIGEST
1. Procuring agency had a reasonable basis to cancel request for proposals
where construction schedule required substantial revision that should lower
performance cost, and thus result in lower prices on recompetition.
2. Protester is not entitled to recover protest costs where agency took
corrective action in response to protest before agency report due date.
DECISION
Goode Construction, Inc. protests the decision of the United States Coast
Guard to cancel request for proposals (RFP) No. DTCG47-01-R-3EFK15, for the
replacement of the central steam plant with natural gas facilities at the
Coast Guard Training Center in Cape May, New Jersey. Goode also requests
reimbursement of the costs it incurred in filing and pursuing a protest
against an earlier award of a contract to Wren, Inc. under the same
solicitation.
We deny the protest and the request for costs.
The RFP, issued as a HUBZone set-aside, required the successful contractor
to decentralize the steam plant before September 15, 2001, the start of the
2002 heating season. Contracting Officer's Statement, B-288655.4 (COS), at
1. The Coast Guard initially made award to Wren. Goode protested to our
Office that the award was improper because the Coast Guard improperly
evaluated its proposal. We denied those protests. Goode Constr., Inc.,
B-288655 et al., Oct. 19, 2001, 2001 CPD para. 186. Goode also filed a protest
with the Small Business Administration (SBA) challenging Wren's HUBZone
contractor status. The SBA upheld the protest by decision of September 21,
which Wren appealed. On October 11, the SBA denied Wren's appeal, affirming
its decision that Wren was not a HUBZone contractor. On October 25, Goode
protested to our Office that the Coast Guard should be required to rescind
the award to Wren and award a contract to Goode. On November 6, the Coast
Guard notified Wren that it was terminating its contract (Goode was notified
of this action on November 8). The agency also decided to cancel the
solicitation and resolicit its requirement in the spring.
Goode now protests the agency's decision to cancel the solicitation,
claiming that the agency instead should make award to Goode as the only
HUBZone offeror under the original competition.
This argument is without merit. A procuring agency properly may reject all
proposals received and cancel an RFP if it has a reasonable basis for doing
so. HBD Indus., Inc., B-242010.2, Apr. 23, 1991, 91-1 CPD para. 400 at 3. Where
cancellation of a solicitation is justified, the fact that a particular
offeror otherwise would have been in line for award does not provide a basis
for precluding the agency from canceling. See Tender Loving Care Ambulance &
Ambulette Co., Inc., B-276571.2, July 17, 1997, 97-2 CPD para. 25 (only small
business remaining in competition is not entitled to award under small
business set-aside where procuring agency had a reasonable basis to cancel
request for proposals); HBD Indus., Inc., supra (sole remaining acceptable
offeror is not entitled to award where agency has a legitimate basis to
cancel procurement).
The Coast Guard states that the primary reason it canceled the solicitation
and will resolicit the requirement is that the construction schedule under
the RFP must be substantially revised. COS at 1. Specifically, the agency
explains, when the solicitation was issued, construction was required to be
completed within 13 months so that the switchover to the central heating
system would be completed by September 15, the start of the 2002 heating
season. However, as a result of Goode's protests to our Office and the SBA,
performance was delayed, and the work now cannot begin until after the 2002
heating season. The agency now expects to issue the solicitation in the
spring, with the work to be performed during the summers of 2002 and 2003,
and completed by December 2003. The agency believes this increased
performance period will reduce the risk associated with the liquidated
damages clause, and therefore will reduce offerors' costs and result in
lower prices. Id.
Full decision text continues on ProtestIntel...