Warden Associates, Inc., B-291440; B-291440.2, December 27, 2002
Case: B-291440
Agency:
Protester: Warden Associates, Inc., B
Date: 2002-12-27
Denied
Warden Associates, Inc., B-291440; B-291440.2, December 27, 2002
TITLE: Warden Associates, Inc., B-291440; B-291440.2, December 27, 2002
BNUMBER: B-291440; B-291440.2
DATE: December 27, 2002
**********************************************************************
Warden Associates, Inc., B-291440; B-291440.2, December 27, 2002
Decision
Matter of: Warden Associates, Inc.
File: B-291440; B-291440.2
Date: December 27, 2002
Harlan Wax for the protester.
Kenneth W. Dodds, Esq., Small Business Administration, for the agency.
Sharon L. Larkin, Esq., and James A. Spangenberg, Esq., Office of the
General Counsel, GAO, participated in the preparation of the decision.
DIGEST
Protest that agency established unreasonably short deadline to respond to
request for quotations issued under the Federal Supply Schedule program is
denied, where protester essentially admits it could have timely responded
but chose not to.
DECISION
Warden Associates, Inc. protests the issuance of a task order by the Small
Business Administration (SBA) under request for quotations (RFQ)
SBAHQ-02-Q-0043 for consulting services related to performing cost
comparisons under Office of Management and Budget Circular A-76. Warden
contends that the RFQ, which sought *a technical and price proposal* under
Warden's General Services Administration (GSA) Federal Supply Schedule
(FSS) contract, did not permit sufficient time for response. Warden also
challenges the selection of the only vendor that submitted a response,
Jefferson Consulting Group.
We deny the protest.
The record includes an SBA requisition, dated July 18, 2002, for a
consultant to assist the agency in the conduct of A-76 cost comparison
studies. The SBA's estimate of the cost of services was approximately
$175,000. AR Tab C, Requisition for Services. However, funding did not
become available, and the requisition therefore was not approved, until
approximately 6 p.m. on Friday, September 27. At 9:15 p.m. that day, the
contracting officer faxed the RFQ to four FSS vendors, including Warden,
and left telephone messages with each vendor as well. Warden claims it
never received the telephone message.
The RFQ sought a *technical and price proposal in accordance with your GSA
schedule contract* for A-76 consulting services. These services included
providing the SBA with an implementation strategy, expert advice, and
training for conducting A‑76 studies. Submissions were due by
Monday, September 30, at 1 p.m.
On Monday morning, September 30, Warden contacted the contracting officer
and sought an extension of time for filing its response to the RFQ or, in
the alternative, permission to submit its response by e-mail. Its
requests were denied. The contracting officer explained that the SBA
needed to place the order that day, which was the last day of the fiscal
year, or else funding would expire. She explained that the SBA was having
difficulties with its e-mail server, and would therefore not accept e-mail
submissions, but told Warden that it could submit its response by
facsimile. As explained below, Warden found this to be unacceptable.
Only one vendor, Jefferson, submitted a response to the RFQ. Jefferson
currently performs related A-76 consulting services for the SBA under a
separate task order. Jefferson's response to the RFQ, which was timely
received by the SBA at 12:50 p.m. on September 30, included a detailed
technical proposal and a quotation to perform the work for approximately
the same amount as the agency estimate. The SBA placed an order for the
services with Jefferson on a time and materials basis, as contemplated by
the RFQ.
Warden timely protested that the SBA had not allowed sufficient response
time to respond to the RFQ. In a supplemental protest, it also challenged
the SBA's issuance of the task order to Jefferson.
Warden first contends that the SBA's establishment of a 3-day response
time violates Federal Acquisition Regulation (FAR) S: 5.203 (requiring a
minimum 30-day response time) and 41 U.S.C. S: 5 (requiring agencies to
advertise for proposals). However, these rules apply to traditional
negotiated procurements and not to the FSS program, which is governed
instead by FAR Subpart 8.4.[1] Computer Prods., Inc., B-284702, May 24,
2000, 2000 CPD P: 95 at 4. Nevertheless, where, as here, an agency
invites firms to submit a *technical and cost proposal* in response to an
RFQ, we will review the agency's actions to ensure that the evaluation is
fair and reasonable and consistent with the terms of the RFQ. Comark Fed.
Sys., B-278343, B-278343.2, Jan. 20, 1998, 98-1 CPD P: 34 at 4-5.
FAR Subpart 8.4 does not require that vendors be permitted a specific
minimum amount of time to respond to an RFQ; what is reasonable and
sufficient depends on the facts and circumstances of the case.
Full decision text continues on ProtestIntel...