Ballast Ham Dredging BV, B-291728; B-291728.2, April 4, 2003
Case: B-291728
Agency:
Protester: Ballast Ham Dredging BV, B
Date: 2003-04-04
Denied
Ballast Ham Dredging BV, B-291728; B-291728.2, April 4, 2003
TITLE: Ballast Ham Dredging BV, B-291728; B-291728.2, April 4, 2003
BNUMBER: B-291728; B-291728.2
DATE: April 4, 2003
**********************************************************************
Ballast Ham Dredging BV, B-291728; B-291728.2, April 4, 2003
Decision
Matter of: Ballast Ham Dredging BV
File: B-291848
Date: April 4, 2003
Simon Boon for the protester.
Joseph A. Gonzales, Esq., Department of the Army, for the agency.
John L. Formica, Esq., and James A. Spangenberg, Esq., Office of the
General Counsel, GAO, participated in the preparation of the decision.
DIGEST
Agency's evaluation of the protester's proposal as marginal under certain
evaluation factors and selection of the awardee's higher-rated, slightly
higher-priced proposal for the award of a contract for dredging were
reasonable and consistent with the terms of the solicitation.
DECISION
Ballast Ham Dredging BV protests the award of a contract to Van Oord ACZ
Marine Contractors BV, under request for proposals (RFP) No.
DACW01-02-R-0067, issued by the Army Corps of Engineers, for maintenance
dredging of the access channel to the Port of Guayaquil, Ecuador. Ballast
Ham argues that the agency's evaluation of its proposal, and the selection
of Van Oord's higher-priced proposal for award, were unreasonable.
We deny the protest.
The RFP provided for the award of a fixed-price contract for the dredging
to be completed within 540 days. The successful contractor will provide
all equipment, materials, and personnel to complete the dredging and
dispose of the dredged materials in accordance with the terms of the RFP.
The solicitation stated that award would be made to the offeror whose
proposal represented the best value, considering price and the following
evaluation factors listed (with one exception) in descending order of
importance: specialized experience on similar type work; dredging
equipment; dredging approach; key personnel experience and qualifications;
organization; and preliminary project schedule.[1] The RFP advised that
to determine the *best value* proposal for award, the agency would
consider all evaluation factors combined (other than price) equal in
importance to price.
The RFP included detailed instructions for the preparation of proposals,
and requested that proposals include separate sections addressing each of
the stated evaluation factors. The solicitation added that the agency
intended to award a contract without conducting discussions and therefore
offerors' initial proposals should contain their best terms with regard to
both price and technical submissions.
The agency received six proposals by the closing date. The proposals were
reviewed, and clarification questions were provided to the offerors. Van
Oord's proposal was evaluated as *above average,* with an identified
*advantage,* under both the specialized experience on similar type work
and dredging equipment factors, and *satisfactory* under the dredging
approach, key personnel experience and qualifications, organization, and
preliminary project schedule factors, at a price of $13,245,597.[2]
Ballast Ham's proposal was also evaluated as *above average,* with an
identified *advantage,* under both the specialized experience on similar
type work and dredging equipment factors, and *satisfactory* under the key
personnel experience and qualifications and organization factors; however,
this proposal was rated *marginal,* with one *significant weakness,* under
the dredging approach factor and *marginal,* with two *deficiencies,*
under the preliminary project schedule factor, at a price of $12,872,087.
AR, Tab I, Source Selection Evaluation Board (SSEB) Report, Dec. 5, 2002,
at 1-3; attachs., Revised Consensus Evaluation Sheets, Van Oord's and
Ballast Ham's Proposals.
In considering the evaluation results, the source selection authority
(SSA) and SSEB noted that the proposals submitted by Van Oord and two
other offerors were technically acceptable or better as initially
submitted, while the proposals of Ballast Ham and the remaining two
offerors had deficiencies and/or weaknesses, such that *discussions would
be necessary to allow them to bring their offers into compliance with the
Solicitation.* The SSA also noted that Van Oord's proposal was evaluated
as above average with advantages under the two most important evaluation
factors (specialized experience and dredging equipment), and that it had
offered a *highly competitive* price (only 3 percent higher than Ballast
Ham's price). With regard to Ballast Ham's proposal, the SSA found that
while it was the lowest-priced proposal, and like Van Oord's proposal had
received *above average* ratings under the two most important evaluation
factors, the proposal contained one significant weakness and two
deficiencies that would need to be addressed through discussions.
Full decision text continues on ProtestIntel...