Bechtel Hanford, Inc., B-292288; B-292288.2; B-292288.3, August 13, 2003
Case: B-292288
Agency:
Protester: Bechtel Hanford, Inc., B
Date: 2003-08-13
Sustained
Bechtel Hanford, Inc., B-292288; B-292288.2; B-292288.3, August 13, 2003
TITLE: Bechtel Hanford, Inc., B-292288; B-292288.2; B-292288.3, August 13, 2003
BNUMBER: B-292288; B-292288.2; B-292288.3
DATE: August 13, 2003
**********************************************************************
Bechtel Hanford, Inc., B-292288; B-292288.2; B-292288.3, August 13, 2003
DOCUMENT FOR PUBLIC RELEASE
The decision issued on the date below was subject to a GAO Protective
Order. This is an interim redacted version that has been approved for
public release; GAO intends to issue a final redacted version at a later
date.
Decision
Matter of: Bechtel Hanford, Inc.
File: B-292288; B-292288.2; B-292288.3
Date: August 13, 2003
Marcia G. Madsen, Esq., David F. Dowd, Esq., and Michael J. Farley, Esq.,
Mayer, Brown Rowe & Maw, and Robert Humphries, Esq., Bechtel Hanford,
Inc., for the protester.
Kenneth B. Weckstein, Esq., Shlomo D. Katz, Esq., and Tammy Hopkins, Esq.,
Epstein Becker & Green, for Washington Closure Company, LLC, an
intervenor.
Gena E. Cadieux, Esq., Joseph B. Schroeder, Esq., Patricia D. Grahm, Esq.,
and Jonathan M. Dreger, Esq., Department of Energy, for the agency.
Scott H. Riback, Esq., and John M. Melody, Esq., Office of the General
Counsel, GAO, participated in the preparation of the decision.
DIGEST
Protest that agency improperly made award in a cost-plus-incentive-fee
acquisition to a firm that submitted a proposal whose cost was found to be
[deleted] unrealistic by the agency is sustained where solicitation called
for evaluation of realism of cost proposals, agency emphasized need for
realism during written and oral discussions, agency never indicated to
offerors during the competition that it would accord little weight to
realism in its source selection, protester relied on agency*s direction in
submitting a proposal that was found very realistic, and agency failed to
adequately document in its selection decision why it discounted the
importance of realism in its source selection.
DECISION
Bechtel Hanford, Inc. (BHI) protests the award of a contract to Washington
Closure Company, LLC (WCC) under request for proposals (RFP) No.
DE-RP06-02RL14300, issued by the Department of Energy (DOE) to acquire
environmental remediation services. BHI maintains that the agency
misevaluated proposals and made an improper source selection decision.
We sustain the protest.
BACKGROUND
DOE occupies a 586 square mile area in southeastern Washington State known
as the Hanford Site, through which flows the Columbia River. The 210
square mile area adjacent to the river is known as the River Corridor.
The agency acquired the Hanford Site in 1943, and for almost 50 years it
was dedicated to the production of plutonium used to construct nuclear
weapons. The agency describes the environmental legacy resulting from
these activities as *multifaceted and immense.* The object of the current
RFP is to acquire environmental remediation services leading, ultimately,
to restoration of the River Corridor area.
The RFP contemplated the award, on a *best value* basis, of a
cost-plus-incentive-fee (CPIF) contract, considering evaluated cost and
several non-cost evaluation criteria, with the non-cost criteria
collectively being significantly more important than evaluated cost. RFP
at M-2.[1] Offerors were required to submit both technical and cost
proposals. Cost proposals were to include estimates based on two
differing assumptions relating to the level of available funding: the
*base case* level of funding--which assumed funding of approximately $150
million per year--and the *40 percent increment* level of
funding--approximately $210 million per year (40 percent higher than the
base case level). RFP at L-21. These two estimates would be averaged
together for purposes of evaluation and award. RFP at M 5-6.
The solicitation included a document designated as attachment 11, which
was a comprehensive list of all tasks to be performed under the contract.
This document included a government estimate, expressed in unescalated
fiscal year 2001 dollars, of the cost for each element of work. The
agency also separately published a government estimate and an accompanying
report relating to the preparation of the estimate (referred to as the
ICE) that was available to offerors through the Internet.[2] DOE engaged
the services of the U.S. Army Corps of Engineers to prepare the estimate,
which is expressed in two ways--a 50-percent confidence level and an
80-percent confidence level--reflecting the degree of certainty the agency
had in the estimates (with the 80-percent confidence level estimate
reflecting greater certainty). AR, exh. 84.
Full decision text continues on ProtestIntel...