Strategic Analysis, Inc., B-292392; B-292392.2, September 3, 2003
Case: B-292392
Agency:
Protester: Strategic Analysis, Inc., B
Date: 2003-09-03
Denied
Strategic Analysis, Inc., B-292392; B-292392.2, September 3, 2003
TITLE: Strategic Analysis, Inc., B-292392; B-292392.2, September 3, 2003
BNUMBER: B-292392; B-292392.2
DATE: September 3, 2003
**********************************************************************
Strategic Analysis, Inc., B-292392; B-292392.2, September 3, 2003
DOCUMENT FOR PUBLIC RELEASE
The decision issued on the date below was subject to a GAO Protective
Order. This redacted version has been approved for public release.
Decision
Matter of: Strategic Analysis, Inc.
File: B-292392; B-292392.2
Date: September 3, 2003
James D. Bachman, Esq., and Ron R. Hutchinson, Esq., Doyle & Bachman, for
the protester.
Michael F. Copley, Esq., and Stuart W. Harris, Esq., Kegler Brown Hill &
Ritter, for LOGTEC, Inc., the intervenor.
Maj. Brent G. Curtis, and Michael D. McGrath, Esq., Department of the Air
Force, for the agency.
Paul I. Lieberman, Esq., and Michael R. Golden, Esq., Office of the
General Counsel, GAO, participated in the preparation of the decision.
DIGEST
Where solicitation expressly contemplated that vendor would not have
certain required non-disclosure agreements (NDA) until after commencement
of performance under task order, and provided criteria for assessing
vendor*s plan to obtain NDAs after issuance of order without calling for
price evaluation adjustments or for any adverse evaluation consequences
for doing so, agency reasonably did not downgrade proposal for including a
highly rated plan to obtain required NDAs after issuance of the order, and
was not required to increase the evaluated cost to the government to
compensate for the alleged transition costs related to the delay in
performance that the solicitation anticipated for obtaining the NDAs.
DECISION
Strategic Analysis, Inc. (SAI) protests the issuance of a 5-year time and
materials task order (to be placed against a General Services
Administration (GSA) federal supply schedule (FSS) contract) to LOGTEC,
Inc., for independent research and development and data mining (IR&D)
support under request for quotations (RFQ)No. FA8652-03-Q-0012, issued by
the Air Force Research Laboratory. SAI protests that the Air Force
misevaluated LOGTEC*s proposal by failing to properly consider the cost
and technical impact of LOGTEC*s need to obtain certain non-disclosure
agreements (NDAs) that are required in order to perform, and that the Air
Force conducted improper discussions with LOGTEC.
We deny the protest.
The RFQ, issued on April 11, 2003, sought quotations to be evaluated on
the basis of three factors, management approach to acquiring NDAs, IR&D
expertise and data mining technical ability, and price respectively on a
30/40/30 percentage weighted basis. The Air Force estimates that there
are approximately 100 required NDAs, and the RFQ statement of work (SOW)
provided that the contractor was required to initiate, update, renew, or
otherwise obtain 80 percent of these agreements prior to beginning the
data mining subtask. RFQ, SOW P: 1.1.1.1. The RFQ also stated that the
government *anticipates that it may take 5-7 months for a contractor with
few existing NDAs to establish the NDAs identified* in the solicitation,
and required that the vendor*s *proposal regarding management approach to
acquiring NDAs shall include a performance plan with progress measures.*
RFQ P: 2(a). Three quotes were received by the amended April 21 deadline,
LOGTEC*s and SAI*s, plus one from a vendor whose technical approach was
evaluated as noncompetitive.
SAI, the incumbent, had in place approximately 40 current required NDAs.
LOGTEC had 90 NDAs, a limited number of which the Air Force believed could
be used for the contract requirements at issue. SAI*s quote was
$2,059,055.70 and LOGTEC*s was $1,532,225.68. SAI*s proposal received a
slightly higher overall technical evaluation resulting in part from the
assessment under the approach to acquiring NDA factor, under which the
evaluators credited SAI for possession of a significant number of executed
NDAs, in conjunction with a solid plan to acquire the required additional
NDAs. LOGTEC*s proposal received a slightly less favorable evaluation
under this factor because LOGTEC did not have in place a comparable base
of required NDAs, but the evaluators credited LOGTEC for its extensive
experience in establishing NDAs, its possession of existing NDAs that
might be usable, and for a solid plan for acquiring and maintaining NDAs,
which included the proposed use of an incumbent consultant whose
credentials added credibility for purposes of acquiring the required
NDAs. AR, Tab 7, Technical Evaluation of LOGTEC, at 1. Neither vendor*s
proposal was evaluated as having any weaknesses under this factor.
Full decision text continues on ProtestIntel...