Lockheed Martin Simulation, Training & Support, B-292836.8; B-292836.9; B-292836.10, November 24, 2004
Case: B-292836.8
Agency:
Date: 2004-11-24
Sustained
Lockheed Martin Simulation, Training & Support, B-292836.8; B-292836.9; B-292836.10, November 24, 2004
TITLE: Lockheed Martin Simulation, Training & Support, B-292836.8; B-292836.9; B-292836.10, November 24, 2004
BNUMBER: B-292836.8; B-292836.9; B-292836.10
DATE: November 24, 2004
**********************************************************************
Decision
Matter of: Lockheed Martin Simulation, Training & Support
File: B-292836.8; B-292836.9; B-292836.10
Date: November 24, 2004
Thomas C. Papson, Esq., Richard B. Oliver, Esq., Alison L. Doyle, Esq.,
Jason N. Workmaster, Esq., Stephen M. Lastelic, Esq., Kevin J. Slattum,
Esq., and Joseph S. Beemsterboer, Esq., McKenna Long & Aldridge LLP, for
the protester.
Rand L. Allen, Esq., Philip J. Davis, Esq., Paul F. Khoury, Esq., Michael
S. Caldwell, Esq., William J. Grimaldi, Esq., Adam J. Rogers, Esq., and
Steven N. Tomanelli, Esq., Wiley Rein & Fielding LLP, for Electronic Data
Systems Information Services, LLC, an intervenor.
Peter F. Pontzer, Esq., Kenneth M. Hyde, Esq., Kimberly Y. Nash, Esq., and
Angela T. Puri, Esq., Department of Housing and Urban Development, for the
agency.
Scott H. Riback, Esq., and John M. Melody, Esq., Office of the General
Counsel, GAO, participated in the preparation of the decision.
DIGEST
1. Protest that agency improperly engaged in post-final proposal revision
(post-FPR) discussions only with awardee is sustained where record shows
that post-FPR exchange resulted in material changes to awardee's proposal.
2. Protest that agency failed to engage in meaningful discussions with
protester is sustained where record shows that agency failed to discuss
weaknesses first identified in a reevaluation of proposals that were based
on earlier proposal language, and also was unreasonably vague in areas
where agency did conduct discussions.
DECISION
Lockheed Martin Simulation, Training & Support, a business unit of
Lockheed Martin Corporation (LMC), protests the award of a contract to
Electronic Data Systems Information Services, LLC (EDS) under request for
proposals (RFP) No. R-OPC-21970, issued by the Department of Housing and
Urban Development (HUD) to acquire information technology (IT) services.
LMC asserts that the agency committed various errors in conducting
discussions, misevaluated proposals, and made an unreasonable source
selection decision.
We sustain the protest.
BACKGROUND
This is the third occasion where we have been called upon to review HUD's
actions in connection with this acquisition. In August 2003, HUD awarded
a contract to EDS under the subject RFP and LMC filed a protest relating
to that award. We sustained the protest, finding that the agency
misevaluated the proposals in numerous respects and appeared to have
applied a double standard in its evaluation; as a consequence, the
agency's source selection decision was not reasonable. We recommended
that the agency reopen the acquisition, engage in discussions with the
offerors, obtain and evaluate revised proposals (being sure to apply a
consistent standard in its evaluation) and make a new source selection
decision. Lockheed Martin Info. Sys., B-292836 et al., Dec. 18, 2003,
2003 CPD P 230.
During the pendency of the initial protest, the agency determined that
proceeding with performance of the EDS contract in the face of the protest
was in the government's best interest. The agency therefore began
transitioning its IT requirements from LMC, which had been the incumbent,
to EDS. At the time of the agency's original decision to proceed with
performance, LMC did not challenge the agency's actions. Subsequently,
and at approximately the same time that the agency initiated its
corrective action, LMC pursued injunctive relief at the United States
Court of Federal Claims, seeking to prevent the further transition of IT
activities from LMC to EDS. The Court did not rule on that dispute
because the parties arrived at a negotiated settlement that suspended
further transition activities until a new award decision could be made.
Thus, following these actions, EDS was performing a portion of HUD's IT
requirements, and LMC the remainder.
In response to our earlier decision, the agency amended the RFP in
numerous significant respects and afforded the offerors an opportunity to
submit revised proposals. Thereafter, both LMC and EDS filed pre-closing
protests, each maintaining that the terms of the reopened competition
provided the other offeror an unfair competitive advantage. Our Office
conducted an alternative dispute resolution (ADR) session in an effort to
settle the protests and allow the agency to proceed with its acquisition.
Full decision text continues on ProtestIntel...