Kilgore Flares Company, B-292944; B-292944.2; B-292944.3, December 24, 2003
Case: B-292944
Agency:
Protester: Kilgore Flares Company, B
Date: 2003-12-24
Denied
Kilgore Flares Company, B-292944; B-292944.2; B-292944.3, December 24, 2003
TITLE: Kilgore Flares Company, B-292944; B-292944.2; B-292944.3, December 24, 2003
BNUMBER: B-292944; B-292944.2; B-292944.3
DATE: December 24, 2003
**********************************************************************
Kilgore Flares Company, B-292944; B-292944.2; B-292944.3, December 24, 2003
DOCUMENT FOR PUBLIC RELEASE
The decision issued on the date below was subject to a GAO Protective
Order. This redacted version has been approved for public release.
Decision
Matter of: Kilgore Flares Company
File: B-292944; B-292944.2; B-292944.3
Date: December 24, 2003
Michael B. Hubbard, Esq., Joseph J. Dyer, Esq., and Robert F. Pezzimenti,
Esq., Seyfarth Shaw, for the protester.
Ronald K. Henry, Esq., Kaye Scholer, for FR Countermeasures, Inc.; and
Richard W. Oehler, Esq., and Eric A. Aaserud, Esq., Perkins Coie, for
Armtec Defense Products Company, intervenors.
Rick Martinelli, Esq., Department of the Navy, for the agency.
Ralph O. White, Esq., and Christine S. Melody, Esq., Office of the General
Counsel, GAO, participated in the preparation of the decision.
DIGEST
Contention that agency wrongly rejected protester*s offer after
determining that the protester was nonresponsible is denied where the
record shows that the agency reasonably concluded that protester had not
clearly established that it could meet the solicitation*s delivery
schedule.
DECISION
Kilgore Flares Company protests the determination that it is not a
responsible offeror, and the resulting rejection of its lowest-priced
offer, by the Department of the Navy under request for proposals (RFP) No.
N00104-03-R-K054, issued to procure two types of flare decoys--known as
MJU-38B and MJU-32B flares (hereinafter, the *38B* and *32B* flares)--for
use as countermeasures for aircraft under attack by heat-seeking missiles.
In finding that Kilgore is not a responsible offeror, the Navy concluded,
primarily, that Kilgore could not meet the delivery schedules here;
Kilgore argues that the agency*s determination lacks a reasonable basis.
We deny the protest.
BACKGROUND
The manufacture of flare decoys involves assembling highly explosive and
unstable materials. Many of the firms that build these flares have
experienced catastrophic explosions resulting in plant shutdowns, missed
deliveries and sometimes, loss of life. After years of successfully
producing these flares, and surviving in a market where other
manufacturers dropped out of the business, Kilgore*s plant suffered a
fatal explosion in April 2001. As a result, its plant was closed while
the incident was investigated, and Kilgore was unable to make deliveries
of flares on two previously-awarded Navy contracts for the 38B and 32B
flares.
As Kilgore was the only remaining firm producing flares for the Navy at
the time of the accident, the Navy was forced to issue Military
Interdepartmental Purchase Requests to the Army*s Crane Ammunition
Activity for its 38B and 32B flares. The Navy explains that the cost of
purchasing its flares from the Army is *significantly higher* than
purchasing flares from the commercial explosives sector. Navy Clearance
Memorandum at 3. This is the environment in which the RFP here was
issued.
On February 5, 2003, the Navy issued the instant RFP for 38B and 32B
flares, seeking offers for the award of a fixed-price contract. The RFP*s
base quantity sought 32,340 of each flare; the RFP also contained two
options--one for each flare--seeking up to 48,150 each. RFP at 2-5. The
RFP advised that award would be made *to the responsible offeror
submitting the lowest priced, technically acceptable offer.* Id. at 70.
The RFP provided explicit guidance on the need for first article testing,
and on the importance of timely deliveries. On first article testing, the
RFP advised potential offerors that they would be required to produce and
deliver a quantity of the flares for government testing unless the
contractor requested, and received from the government, a waiver of the
requirement because the contractor had produced *supplies identical or
similar to* those solicited. Id. at 38. Under the circumstances here,
Kilgore was the only potential offeror likely to be in a position to
obtain a waiver of the first article test requirement.
On timely deliveries, the RFP advised potential offerors that there was a
critical need for the timely delivery of these flares, and warned that
offerors who take exception to the delivery schedule in the solicitation
would not be considered for award. Id. at 6.
Full decision text continues on ProtestIntel...