Resource Consultants, Inc., B-293073.3; B-293073.5; B-293073.6, June 2, 2004
Case: B-293073.3
Agency:
Protester: Resource Consultants, Inc., B
Date: 2004-06-02
Sustained
Resource Consultants, Inc., B-293073.3; B-293073.5; B-293073.6, June 2, 2004
TITLE: Resource Consultants, Inc., B-293073.3; B-293073.5; B-293073.6, June 2, 2004
BNUMBER: B-293073.3; B-293073.5; B-293073.6
DATE: June 2, 2004
**********************************************************************
DOCUMENT FOR PUBLIC RELEASE
The decision issued on the date below was subject to a GAO Protective
Order. This redacted version has been approved for public release.
Decision
Matter of: Resource Consultants, Inc.
File: B-293073.3; B-293073.5; B-293073.6
Date: June 2, 2004
John S. Pachter, Esq., Jonathan D. Shaffer, Esq., Sophia R. Zetterlund,
Esq., Erin R. Karsman, Esq., and Richard C. Johnson, Esq., Smith Pachter
McWhorter & Allen, for the protester.
Agnes P. Dover, Esq., Todd R. Overman, Esq., and Gary A. Campbell, Esq.,
Hogan & Hartson, an intervenor.
Robert L. Duecaster, Esq., Department of the Army, for the agency.
Ralph O. White, Esq., and Christine S. Melody, Esq., Office of the General
Counsel, GAO, participated in the preparation of the decision.
DIGEST
Protester's contention that the awardee's final revised price effectively
altered its technical approach, even though offerors were not allowed to
make changes to their technical proposals, is sustained where the record
shows that the awardee's final price proposal shifted the mix of personnel
used to perform the contract, and significantly decreased the staffing it
proposed to use for one type of work covered by the contract.
DECISION
Resource Consultants, Inc. (RCI) protests the award of a contract to Titan
Corporation, Enterprise Services and Solutions Sector, by the Department
of the Army under solicitation No. DASW01-03-R-0040, for desktop support
services to the Army's Information Management Support Center. RCI argues
that the Army's evaluation of Titan's revised price proposal was
unreasonable.
We sustain the protest.
BACKGROUND
The RFP here was issued on May 23, 2003, and covered six separate lots of
effort designed to consolidate desktop service support operations for
approximately 80 agencies within Headquarters, Department of the Army.
Lot I of the solicitation, the portion of the work at issue in this
protest, contemplated a single-award,
indefinite-delivery/indefinite-quantity contract for desktop support
services for a base period of 2 years, plus five 1-year options. RFP at
2.
The solicitation sought performance-based solutions to providing desktop
support services to the Army, and requested that offerors submit
fully-burdened hourly labor rates for their employees. The solicitation
also stated that all task and delivery orders under the Lot I contract
would be issued on either a fixed-price or time-and-materials (T&M)
basis.
For reasons discussed in greater detail below, the particular pricing
requirements of this solicitation--both as initially issued, and as
ultimately amended--are relevant to this protest. Initially, offerors
were required to submit five discrete components of price for the Lot I
work (and for each of the option years within Lot I). These were:
(1) a fixed price for the work (see, e.g., CLIN 0001AA);
(2) a T&M price for the work (CLIN 0001AB);
(3) an amount for other direct costs associated with performing the work
on a
fixed-price basis (CLIN 0001AC);
(4) an amount for general and administrative (G&A) costs to be added to
other direct costs associated with performing the work on a fixed-price
basis
(CLIN 0001AD); and,
(5) a price for performing after-hours work on a fixed-price basis
(CLIN 0001AE).
RFP at 6-8. Because the solicitation's pricing schedule requested both
fixed and T&M prices for the work, the total obtained by adding the prices
submitted for each of these CLINs was roughly twice the total expected
price for this effort.
The RFP advised potential offerors that award would be "based on a best
value analysis" of three factors: management/technical, past performance,
and cost/price. RFP amend. 3, at 6. The RFP also advised that the
management/technical factor was more important than the past performance
factor, and that management/technical and past performance combined were
more important than cost/price. Id. at 9.
Seven proposals were received by the initial due date of June 23, 2003,
and five of them were included in the competitive range.
Full decision text continues on ProtestIntel...