Oregon Electric Construction, Inc. dba Integrated Systems Group, B-294279, September 27, 2004
Case: B-294279
Agency:
Protester: Oregon Electric Construction, Inc. dba Integrated Systems Group, B
Date: 2004-09-27
Denied
B-294279
Sep 27, 2004
Jump To
VIEW DECISION
DOWNLOADS
RELATED PAGES
GAO CONTACTS
Highlights
Oregon Electric Construction, Inc. dba Integrated Systems Group (Integrated) protests the rejection of its apparent low bid as nonresponsive under invitation for bids (IFB) No.R6-9-04-07, issued by the Department of Agriculture, Forest Service, for improvement of the Quinault wastewater collection and treatment facility in Washington. Integrated contends that the agency unreasonably determined that its bid cover letter rendered uncertain whether the firm intended to perform in accordance with the solicitation's requirements for operation and maintenance by the contractor of the wastewater treatment plant.
We deny the protest.
View Decision
B-294279, Oregon Electric Construction, Inc. dba Integrated Systems Group, September 27, 2004
Decision
Matter of: Oregon Electric Construction, Inc. dba Integrated Systems Group
File: B-294279
Date: September 27, 2004
Darin D. Honn, Esq., and Jason W. Alexander, Esq., Sussman Shank, for the protester.
Mark G. Garrett, Esq., Department of Agriculture, for the agency.
Susan K. McAuliffe, Esq., and Christine S. Melody, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.
DIGEST
Agency properly rejected bid as nonresponsive where qualification in bid cover letter rendered bid ambiguous; qualification made it uncertain whether bidder unequivocally offered to perform in accordance with terms of solicitation amendment.
DECISION
Oregon Electric Construction, Inc. dba Integrated Systems Group (Integrated) protests the rejection of its apparent low bid as nonresponsive under invitation for bids (IFB) No.R6-9-04-07, issued by the Department of Agriculture, Forest Service, for improvement of the Quinault wastewater collection and treatment facility in Washington. Integrated contends that the agency unreasonably determined that its bid cover letter rendered uncertain whether the firm intended to perform in accordance with the solicitation's requirements for operation and maintenance by the contractor of the wastewater treatment plant.
We deny the protest.
The IFB, issued on March 5, 2004, contemplated the award of a fixed-price contract for a base item (for improvements to the wastewater treatment facility) and two option items (for grinder pump station improvements and drain field expansion). In addition, the amended IFB called for the operation and maintenance of the wastewater treatment plant. Specifically, amendment No. 3 to the IFB provided that
the contractor
shall be responsible for the operation and maintenance of the Quinault wastewater treatment plant from the effective date of the notice to proceed of the Base Item until 3 months after final acceptance by the Contracting Officer of the Base Item.
IFB amend. 3, C.6.
Integrated acknowledged receipt of amendment No. 3. Its bid cover letter, however, provided terms different from that amendment's plant operation terms. In particular, the bid cover letter provided that "[o]peration of the plant is included for duration of the construction project until 3 months after substantial completion." Integrated Bid Cover Letter, Apr. 27, 2004, at 1.
The agency found that the cover letter statement materially qualified Integrated's bid, specifically noting that the offered period--3 months after "substantial completion"--was materially different from the performance period called for by the amended IFB--3 months after final acceptance of the base item. The agency found that the different terms not only limited Integrated's performance risk, but also lessened the rights of the agency under the amended solicitation's "final acceptance" provision. In this regard, under the amended IFB, the agency was to maintain control of the timing of the termination of the contractor's plant operation period, since it was tied to an affirmative action by the agency-- i.e. , final acceptance of the base item work. The agency determined that Integrated's bid was ambiguous and rejected it as nonresponsive. This protest followed.
To be responsive and considered for award, a bid must contain an unequivocal offer to perform, without exception, the exact thing called for in the solicitation, so that, upon acceptance, the contractor will be bound to perform in accordance with all of the IFB's material terms and conditions. If in its bid (including its bid cover letter), a bidder conditions or modifies a material solicitation requirement (such as a performance period), limits its liability to the government, or limits the rights of the government under a resulting contract, then the bid must be rejected as nonresponsive. See Tel-Instrument Elecs. Corp. , B291309, B-291309.2, Nov. 20, 2002, 2002 CPD 203 at2-3; Interstate Constr., Inc. , B281465, Feb. 10, 1999, 99-1 CPD 31 at 2; Balantine's South Bay Caterers, Inc. , B250223, Jan. 13, 1993, 93-1 CPD 39
at 3-4.