Cooperativa Muratori Riuniti, B-294980; B-294980.2, January 21, 2005
Case: B-294980
Agency:
Protester: Cooperativa Muratori Riuniti, B
Date: 2005-01-21
Sustained
Cooperativa Muratori Riuniti, B-294980; B-294980.2, January 21, 2005
TITLE: Cooperativa Muratori Riuniti, B-294980; B-294980.2, January 21, 2005
BNUMBER: B-294980; B-294980.2
DATE: January 21, 2005
**********************************************************************
Decision
Matter of: Cooperativa Muratori Riuniti
File: B-294980; B-294980.2
Date: January 21, 2005
Reed L. von Maur, Esq., for the protester.
Susan L. Schor, Esq., and Laurence Schor, Esq., McManus, Schor, Asmar &
Darden, for Impresa Pizzarotti & C. S.p.A., an intervenor.
Damon Martin, Esq., and Shivaun White, Esq., Naval Facilities Engineering
Command, for the agency.
Jennifer D. Westfall-McGrail, Esq., and Christine S. Melody, Esq., Office
of the General Counsel, GAO, participated in the preparation of the
decision.
DIGEST
1. In evaluating proposals for construction work, agency has not provided
a reasonable basis for distinguishing between offerors' experience in
performing multiple projects at multiple sites under a single contract and
offerors' experience in performing multiple projects at multiple sites
under multiple contracts, particularly where solicitation called for
performance at two separate work sites.
2. Protest against evaluation of past performance is sustained where
record reveals that protester's past performance was re-rated by the
evaluators on a different scale and in response to different questions
than those posed to the references, and it is not clear that the new
ratings were reasonably based.
3. Evaluators reasonably rated protester's proposed construction schedule
as good, as opposed to excellent, where they determined that protester had
offered an accelerated schedule, but had failed to offer evidence that it
had thought through the implications of that schedule with regard to
matters such as staffing.
DECISION
Cooperativa Muratori Riuniti (CMR) protests the evaluation of its proposal
and the award of a contract to Impresa Pizzarotti & C. S.p.A. (Pizzarotti)
under request for proposals (RFP) No. N33191-04-R-4004, issued by the
Department of the Navy for construction of two facilities at Aviano Air
Force Base in Italy. The protester takes issue with the agency's
evaluation of its technical proposal.
We sustain the protest.
BACKGROUND
The RFP, which contemplated the award of a fixed-price contract, requested
prices for a base and six optional line items. Contract line item No.
(CLIN) 0001 (the base item) and CLIN 0002 sought prices for the work
associated with "Phase II" of the effort, construction of a personnel
alert holding area. CLINs 0003-0007 sought prices for the work associated
with "Phase I" of the effort, construction of a heavy drop rigging
facility. The agency notes that the sites at which the two "phases" will
be performed are approximately a half-mile apart. The solicitation
provided for exercise of CLIN 0002 within 180 days after contract award,
CLIN 0003 within
365 days after contract award, and CLINs 0004-0007 within 90 days after
exercise of CLIN 0003.
The RFP provided for award to the offeror whose proposal represented the
best value to the government. Three equally weighted
factors--organizational experience, organizational past performance, and
schedule--were to be considered in the evaluation of technical proposals;
taken together, these factors were to be of approximately equal weight to
price in the evaluation. Proposals were to be rated both overall and with
regard to each evaluation factor as excellent, good, satisfactory,
marginal, or poor.
Six offerors responded to the RFP. The technical evaluation board (TEB)
assigned Pizzarotti's technical proposal ratings of excellent for past
performance and schedule and a rating of good for organizational
experience; overall, the TEB rated the proposal as excellent. The TEB
rated CMR's proposal as good for past performance and schedule and as
satisfactory for organizational experience, resulting in an overall
technical rating of good. The other proposals were rated lower. CMR's
overall price, inclusive of all options, of [deleted] was [deleted], while
Pizzarotti's price of *20,716,210 was [deleted]. The source selection
board determined that the additional quality of Pizzarotti's proposal
outweighed the price difference between the two proposals and selected it
for award. On September 23, 2004, the Navy notified Pizzarotti and CMR
that Pizzarotti had been awarded a contract for CLINs 0001 and 0002.
Full decision text continues on ProtestIntel...