Park Tower Management Ltd., B-295589; B-295589.2, March 22, 2005
Case: B-295589
Agency:
Protester: Park Tower Management Ltd., B
Date: 2005-03-22
Denied
Park Tower Management Ltd., B-295589; B-295589.2, March 22, 2005
TITLE: Park Tower Management Ltd., B-295589; B-295589.2, March 22, 2005
BNUMBER: B-295589; B-295589.2
DATE: March 22, 2005
**********************************************************************
Decision
Matter of: Park Tower Management Ltd.
File: B-295589; B-295589.2
Date: March 22, 2005
J. Randolph MacPherson, Esq., Michael J. Noonan, Esq., and James S.
DelSordo, Esq., Halloran & Sage LLP, for the protester.
Benjamin N. Thompson, Esq., and Jennifer M. Miller, Esq., Wyrick Robbins
Yates & Ponton LLP, for LB&B Associates, Inc., an intervenor.
Ruth Kowarski, Esq., GSA-Public Buildings Service, for the agency.
Paul E. Jordan, Esq., and John M. Melody, Esq., Office of the General
Counsel, GAO, participated in the preparation of the decision.
DIGEST
1. Where solicitation for building maintenance services provided for
evaluation of comparability of buildings under prior maintenance contracts
to building under solicited requirement, including equipment maintained,
agency reasonably determined that awardee's building was comparable,
despite fact that equipment awardee maintained was located in adjacent
building, not in building submitted for consideration.
2. Evaluation of offerors' preventative maintenance plans was
unobjectionable where neither offeror's plan included all required
information, and agency scored protester's plan more favorably because it
contained more information than awardee's.
3. Where offeror proposed to hire specific individuals employed by
incumbent contractor, but failed to include required qualification and
other information, agency reasonably considered information from outside
proposal to fill in gaps.
4. Protester's allegation that agency improperly held discussions only
with awardee after submission of final revised proposals is denied where
record shows that contracting officer communicated with awardee only to
clarify status of its commitments from proposed personnel.
Park Tower Management Ltd. protests the award of a contract to LB&B
Associates, Inc. under request for proposals (RFP) No. GS-02P-00-PLC-0191,
issued by the General Services Administration (GSA) for mechanical and
elevator maintenance services at the Daniel Patrick Moynihan U.S.
Courthouse in New York City. Park Tower challenges the technical
evaluation, discussions, and award.
We deny the protest.
The solicitation, which contemplated the award of a fixed-price contract
for a base period (3 years) with two 3-year options, sought proposals for
all management, supervision, labor, material, repair parts, tools, and
equipment for mechanical and elevator maintenance services at the Moynihan
Courthouse. The solicitation was issued in two phases, the first being a
request for qualifications (RFQ), and the second an RFP for all those
found qualified under the RFQ. Under the RFQ, prospective offerors were
required to submit evidence of their experience in performing full
mechanical maintenance services in at least three buildings considered
comparable to the Moynihan Courthouse.[1] Under the RFP, successful RFQ
offerors were required to submit proposals, which were to be evaluated
under a price factor and the following five technical factors, listed in
descending order of importance--past performance (weighted at 55 of a
possible 95 percent), preventive maintenance (PM) plan (10A percent),
staffing and authority plan (10 percent), quality control (QC) plan
(10A percent), and customer service plan (10 percent). The technical
factors, when combined, were approximately equal in weight to price.
Award was to be made to the offeror whose proposal was found to be the
"best value" to the government.
Eight offerors, including Park Tower and LB&B, submitted successful
qualification statements in response to the RFQ, and both therefore were
among the five firms that submitted proposals under the RFP phase of the
solicitation. After the initial evaluation of proposals, the agency
conducted two rounds of discussions and obtained two proposal revisions.
Proposals were scored on a 10-point scale for each technical factor. The
source selection evaluation board (SSEB) then convened to reach a
consensus score for each proposal under each factor, which scores were
then multiplied by the applicable factor weights.
Full decision text continues on ProtestIntel...