Restoration and Closure Services, LLC, B-295663.6; B-295663.12, April 18, 2005
Case: B-295663.6
Agency:
Date: 2005-04-18
Dismissed
Restoration and Closure Services, LLC, B-295663.6; B-295663.12, April 18, 2005
TITLE: Restoration and Closure Services, LLC, B-295663.6; B-295663.12, April 18, 2005
BNUMBER: B-295663.6; B-295663.12
DATE: April 18, 2005
**********************************************************************
Decision
Matter of: Restoration and Closure Services, LLC
File: B-295663.6; B-295663.12
Date: April 18, 2005
William B. Snyder, Esq., and Robert P. Murrian, Esq., Kramer, Rayson,
Leake, Rodgers & Morgan, LLP, for the protester.
Andrew P. Hallowell, Esq., Pamela J. Mazza, Esq., and Jennifer M.
Morrison, Esq., Piliero, Mazza & Pargament, PLLC, for LATA/Parallax
Portsmouth, the intervenor.
Gena E. Cadieux, Esq., Renee S. Holland, Esq., Joseph A. Lenhard, Esq.,
and Beth A. Kelly, Esq., Department of Energy, for the agency.
John L. Formica, Esq., Charles W. Morrow, Esq., Guy R. Pietrovito, Esq.,
and James A. Spangenberg, Esq., Office of the General Counsel, GAO,
participated in the preparation of the decision.
DIGEST
1. Consultants' applications for admission to protective order are denied
where the applications agreed to restrict the consultants' activities only
with regard to the particular site for the procurement being protested,
and thus permitted the consultants to engage or assist in the preparation
of proposals for the same type of work at other sites where a party to the
protest may be a competitor.
2. Protest challenging the agency's evaluation of the protester's
proposal on the basis that, although the solicitation did not prescribe or
suggest a particular technical approach, the agency was predisposed
towards a particular technical solution, is dismissed where there is no
reasonable possibility that the protester was prejudiced by the alleged
unreasonable evaluation because, even if the protester's proposal had
received the maximum points under the contested areas of evaluation, its
proposal would have remained lower rated and significantly higher in cost
than the proposal selected for award.
DECISION
Restoration and Closure Services, LLC (RCS) protests the evaluation of its
proposal and award of a contract to any other firm, under request for
proposals (RFP) No. DE-RP24-040H20179, issued by the Department of Energy
(DOE), for environmental remediation services at DOE's Portsmouth, Ohio
site. [1]
We dismiss the protest.
BACKGROUND
The Portsmouth Gaseous Diffusion Plant is part of the Portsmouth site, and
was operated by DOE and its predecessor agencies as "a uranium enrichment
plant . . . to supply both high- and low-enriched uranium for defense
purposes and commercial nuclear fuel sales." The operation of the
Portsmouth plant "resulted in the generation of significant quantities of
radioactive, hazardous, and mixed waste," with the activities at the plant
causing the "contamination of equipment, facilities, soil, and ground
water with radioactive and hazardous constituents." RFP S C.2.0.
The contractor will be required to provide all personnel, facilities,
equipment, materials and supplies (with the exception of that set forth in
the contract to be furnished by DOE) to accomplish the remediation
services "in a safe, integrated, effective and efficient manner." RFP S
C.2.0.3. The RFP specified that the contractor would have "responsibility
for total performance under this contract, including determining the
specific methods for accomplishing the work within the requirements of the
contract." RFP S C.2.0.1. The solicitation also informed offerors that
the contractor would be "required to comply with all applicable Federal
and State laws and regulations, DOE Directives, permits, agreements and
Orders with regulators (both State and Federal)." Id.
The RFP provided for the award of a cost-plus-incentive-fee contract for
the Portsmouth site to the offeror submitting the proposal representing
the best value to the agency based upon the RFP's technical evaluation
criteria and evaluated cost, with the technical evaluation criteria being
significantly more important than evaluated cost. In this regard, the
solicitation listed the following technical evaluation criteria in
descending order of importance: technical approach, integration and
schedule; key personnel; experience; project and risk management; and past
performance.
The solicitation included detailed instructions for the preparation of
proposals. With regard to technical proposals, the solicitation, while
stating that "[t]he offeror shall describe its technical approach to
address all SOW [statement of work] activities," specifically identified
four aspects of the SOW, and informed offerors that for these aspects they
were to "address in more detail its work processes, methods, and
innovations." RFP S L.17.I.
Full decision text continues on ProtestIntel...