B-297011.3; B-297011.4, Nicholson/Soletanche Joint Venture, April 20, 2006
Case: B-297011.3
Agency:
Protester: B
Date: 2006-04-20
Denied
B-297011.3; B-297011.4, Nicholson/Soletanche Joint Venture, April 20, 2006
TITLE: B-297011.3; B-297011.4, Nicholson/Soletanche Joint Venture, April 20, 2006
BNUMBER: B-297011.3; B-297011.4
DATE: April 20, 2006
**************************************************************************
B-297011.3; B-297011.4, Nicholson/Soletanche Joint Venture, April 20, 2006
DOCUMENT FOR PUBLIC RELEASE
The decision issued on the date below was subject to a GAO Protective
Order. This redacted version has been approved for public release.
Decision
Matter of: Nicholson/Soletanche Joint Venture
File: B-297011.3; B-297011.4
Date: April 20, 2006
Brian P. Waagner, Esq., Elizabeth M. Gill, Esq., and J. Michael
Littlejohn, Esq., Wickwire Gavin, P.C., for the protester.
Robert K. Cox, Esq., Robert G. Barbour, Esq., Kevin J. McKeon, Esq., and
Hanna L. Blake, Esq., Watt, Tieder, Hoffar & Fitzgerald, LLP, for Brayman
Construction Corporation, an intervenor.
Willie J. Williams, Esq., United States Army Corps of Engineers, for the
agency.
Linda S. Lebowitz, Esq., and Michael R. Golden, Esq., Office of the
General Counsel, GAO, participated in the preparation of the decision.
DIGEST
Protest is denied where the agency reasonably evaluated proposals in
accordance with the terms of the solicitation and where the solicitation
provided that the combined technical evaluation factors were significantly
more important than price, the agency reasonably selected for award a
higher technically rated, slightly higher priced proposal.
DECISION
Nicholson/Soletanche Joint Venture (NSJV) protests the award of a contract
to Brayman Construction Corporation (BCC) under request for proposals
(RFP) No. W91237-05-R-0005, issued by the United States Army Corps of
Engineers for dam safety assurance requirements at Bluestone Dam in
Hinton, West Virginia. NSJV protests the evaluation of proposals and the
selection of BCC's higher technically rated, slightly higher priced
proposal for award.
We deny the protest.[1]
BACKGROUND
In this procurement, the Bluestone Dam, which is over 50 years old, is to
be upgraded to meet current engineering standards. More specifically, the
dam, which is comprised of concrete monoliths, is to be renovated through
the installation of high capacity rock anchors which will prevent the dam
from overturning or sliding downstream during extreme flood events. Under
the contract, 150 multi-strand, steel-cabled anchors will be installed.
Because the alignment of the anchors is critical, the anchor holes will be
drilled using a procedure called "directional drilling," which will allow
the holes to be drilled with greater precision.
The RFP was issued on March 4, 2005 and contemplated the award of a
fixed-price contract to the offeror whose proposal conformed to the RFP
and was determined to be most advantageous to the government, considering
price and the following technical evaluation factors: (1) planned
technical execution of key work elements; (2) past performance; and (3)
project management, quality control, key personnel, and schedule. (These
evaluation factors were listed in descending order of importance, with
factor (1) being considered significantly more important than factors (2)
and (3).)
Factor (1)--planned technical execution of key work elements--contained
the following three subfactors, listed in descending order of importance:
(1) drilling techniques; (2) anchor installment; and (3) site use and
access. As relevant here, under the drilling techniques subfactor, an
offeror was to describe the directional drilling method to be used to meet
specified drilling tolerances and to substantiate that the directional
drilling method would have real time survey control and directional
correction. The RFP, as amended, stated that the directional drilling
"should" be performed by a firm which had at least 3 years of experience
engaged in directional drilling; the amended RFP required the driller to
have drilled holes using directional drilling techniques at specified
drilling tolerances on at least two projects. RFP amend. 3, at 2.
Factor (2)--past performance--required an offeror to provide a list of
relevant projects, current or completed, in the past 8 years that best
demonstrated the firm's performance with "this type or similar types" of
projects. Id. The amended RFP stated that an offeror "should" include in
its proposal information related to its prior experience with installing
high capacity anchors, with designing anchor heads for such anchors, and
with installing full length corrosion protection.
Full decision text continues on ProtestIntel...