B-297235; B-297235.2, Global, A 1st Flagship Company, December 27, 2005
Case: B-297235
Agency:
Protester: B
Date: 2005-12-27
Sustained
B-297235; B-297235.2, Global, A 1st Flagship Company, December 27, 2005
TITLE: B-297235; B-297235.2, Global, A 1st Flagship Company, December 27, 2005
BNUMBER: B-297235; B-297235.2
DATE: December 27, 2005
***********************************************************************
B-297235; B-297235.2, Global, A 1st Flagship Company, December 27, 2005
DOCUMENT FOR PUBLIC RELEASE
The decision issued on the date below was subject to a GAO Protective
Order. This redacted version has been approved for public release.
Decision
Matter of: Global, A 1^st Flagship Company
File: B-297235; B-297235.2
Date: December 27, 2005
William A. Roberts III, Esq., Richard B. O'Keeffe, Jr., Esq., Michael S.
Caldwell, Esq., and William J. Grimaldi, Esq., Wiley Rein & Fielding LLP,
for the protester.
Michael J. Gardner, Esq., Troutman Sanders LLP, for George G. Sharpe,
Inc., an intervenor.
Robert J. McMullen, Esq., and Lori S. Chofnas, Esq., Department of the
Navy, for the agency.
Glenn G. Wolcott, Esq., and Michael R. Golden, Esq., Office of the General
Counsel, GAO, participated in the preparation of the decision.
DIGEST
In procurement that placed greater importance on technical factors,
agency's establishment of a competitive range of one, which consisted of
the awardee's technically unacceptable initial proposal and which excluded
protester's "highly acceptable" technical proposal, on the basis that
protester's evaluated cost/price was 15 percent higher than the awardee's,
was not reasonable where the agency's cost/price evaluation reflected
various flaws and erroneous assumptions.
DECISION
Global, A 1^st Flagship Company protests the Department of the Navy's
award of a contract to George G. Sharpe, Inc. under request for proposals
(RFP) No. N00140-05-R-0042. The solicitation sought proposals to operate
and maintain East Coast inactive ships for the Naval Inactive Ship
Management Office (NISMO) in Philadelphia, Pennsylvania. Global maintains
that the agency's establishment of a competitive range consisting of only
Sharpe's proposal reflected various evaluation errors and lacked a
reasonable basis.
We sustain the protest.
BACKGROUND
In May 2005, the agency issued solicitation No. N00140-05-R-0042 seeking
proposals to operate and maintain East Coast inactive ships under a
cost-reimbursement contract for a base period and four 1-year option
periods. The solicitation provided that the successful offeror will
furnish direct labor, supervision, administrative support, and (with the
exception of government furnished property) all materials necessary to
perform the solicitation's requirements. RFP at 16. Global is the
incumbent contractor for the protested procurement; Sharpe holds a similar
contract for operation and maintenance of inactive ships on the West
Coast.
The solicitation stated that proposals would be evaluated on the basis of
cost/price and the following technical evaluation factors which were
listed in descending order of importance: technical and management
approach; corporate experience; past performance;[1] personnel resources,
and small business participation. RFP at 106. Offerors were advised that
technical factors were more important than cost/price. Id. The
solicitation further provided that "[i]f [an] offeror's proposal is
determined unacceptable in any of the technical evaluation factors and/or
subfactors, the proposal may not be considered for award." RFP at 107.
With regard to cost/price proposals, the solicitation listed the
government's estimated levels of required staffhours, by labor category
and contract period;[2] offerors were required to propose labor rates, by
contract period, for the various labor categories. With regard to costs
for materials, the solicitation contained what the contracting officer
described as "plug-in" numbers, Hearing Transcript (Tr.) at 21;[3] that
is, numbers that, for purposes of the cost/price evaluation, would be
applied to all offerors' proposals.[4] However, the solicitation did not
specifically identify the items the government intended to be reflected in
the materials "plug-in" numbers.[5] In this regard, the solicitation
stated: "the term `material' includes supplies, equipment, hardware,
automatic data processing equipment, and software." RFP at 62. However,
the solicitation also stated, "The Government shall furnish all
[necessary] tools/equipment/vehicles/ property/ADP/other equipment, as
specified in Attachments 6, 7, 8 and 9. . . . In the event the material is
not available, the Contractor is authorized to procure material which will
be reimbursed as an Other Direct Cost (ODC)." RFP at 29.