B-297391.2; B-297391.3, East-West Industries, Inc., July 19, 2006
Case: B-297391.2
Agency:
Protester: B
Date: 2006-07-19
Denied
B-297391.2; B-297391.3, East-West Industries, Inc., July 19, 2006
TITLE: B-297391.2; B-297391.3, East-West Industries, Inc., July 19, 2006
BNUMBER: B-297391.2; B-297391.3
DATE: July 19, 2006
*****************************************************************
B-297391.2; B-297391.3, East-West Industries, Inc., July 19, 2006
DOCUMENT FOR PUBLIC RELEASE
The decision issued on the date below was subject to a GAO Protective
Order. This redacted version has been approved for public release.
Decision
Decision
Matter of: East-West Industries, Inc.
File: B-297391.2; B-297391.3
Date: July 19, 2006
Philip M. Dearborn, Esq., Sandeep S. Kathuria, Esq., and Jennifer L.
Andrews, Esq., Piliero, Mazza & Pargament, PLLC, for the protester.
Robert A. Brunette, Esq., for Regent Manufacturing, Inc., an intervenor.
Maj. Jeffrey Branstetter, Maj. Paul W. Knoth, James C. Caine, Esq., and
Maj. LaChandra C. Richardson, Department of the Air Force, for the agency.
Paul E. Jordan, Esq., and John M. Melody, Esq., Office of the General
Counsel, GAO, participated in the preparation of the decision.
DIGEST
1. Evaluation of protester's proposal under past performance evaluation
factor was unobjectionable where agency reasonably concluded that only one
of four prior contracts was of a magnitude and complexity essentially the
same as the solicitation's, and thus met the solicitation's definition of
very relevant; two of the remaining contracts were reasonably evaluated as
only relevant and semi-relevant due to lesser magnitudes of effort, and
the fourth contract was reasonably evaluated as not relevant because it
was completely unrelated to the solicitation's work.
2. Evaluation of awardee's past performance and risk was reasonable,
notwithstanding protester's identification of alleged quality, safety, and
delivery issues, where contracting officials did not have personal
knowledge of majority of the issues, and fully considered those of which
they were aware in finding no negative impact on awardee's past
performance rating.
DECISION
East-West Industries, Inc. protests the award of a contract to Regent
Manufacturing, Inc. under request for proposals (RFP) No.
FA8518-04-R-70801, issued by the Department of the Air Force for
multi-aircraft canopy cranes (MACC). East-West challenges the past
performance and risk evaluations of its and Regent's proposals.
We deny the protest.
BACKGROUND
MACCs are used to remove and install various components on numerous types
of aircraft, including canopies, ejection seats, wings, stabilizers,
rotors, and other components, with sufficient clearance to preclude
contact with all primary aircraft structures, such as landing gears, fuel
tanks, and maintenance stands.[1]
The RFP, a total small business set-aside, contemplated the award of a
requirements-type contract with a basic period to include two first
articles and related materials, with four options, for a total of 360
production units. Proposals were to be evaluated under four
factors--technical, proposal risk, past performance, and price. Technical
acceptability was to be determined based on whether the proposed design
met the requirements for physical characteristics, system reliability, and
system maintainability. Under the proposal risk factor, the agency was to
assess the risk associated with the offeror's proposed approach as it
related to disruption of schedule, increased cost, or degradation of
performance.[2] Under the past performance factor, the agency was to
consider the relevance of offerors' prior contracts to the proposed
effort, together with the quality of performance of those contracts, in
assessing its confidence in the offerors' ability to successfully
accomplish the proposed effort.[3] Once a proposal was determined to be
technically acceptable, award was to be made on a "best value" basis, with
tradeoffs among the remaining factors. Under this procedure, risk and past
performance were considered equal to each other and significantly more
important than price.
Six offerors, including East-West and Regent, submitted proposals by the
original closing time in 2004. Based on the initial evaluation, all
proposals were considered technically unacceptable and the agency issued
evaluation notices (EN). All six offerors responded, but one was
determined not to meet the small business size standard and its proposal
was eliminated. After several rounds of final proposal revisions (FPR) and
additional ENs, the proposals of East-West, Regent, and a third offeror
(not relevant here) were included in the competitive range. The evaluators
rated both East-West's and Regent's proposals as low risk and very
good/significant confidence.
Full decision text continues on ProtestIntel...