B-298583; B-298583.2, SunEdison, LLC, October 30, 2006
Case: B-298583
Agency:
Protester: B
Date: 2006-10-30
Sustained
B-298583; B-298583.2, SunEdison, LLC, October 30, 2006
TITLE: B-298583; B-298583.2, SunEdison, LLC, October 30, 2006
BNUMBER: B-298583; B-298583.2
DATE: October 30, 2006
******************************************************
B-298583; B-298583.2, SunEdison, LLC, October 30, 2006
DOCUMENT FOR PUBLIC RELEASE
The decision issued on the date below was subject to a GAO Protective
Order. This redacted version has been approved for public release.
Decision
Matter of: SunEdison, LLC
File: B-298583; B-298583.2
Date: October 30, 2006
Gerald H. Werfel, Esq., Pompan, Murray & Werfel, PLC, for the protester.
Gary R. Allen, Esq., Department of the Air Force, for the agency.
Jennifer D. Westfall-McGrail, Esq., and Christine S. Melody, Esq., Office
of the General Counsel, GAO, participated in the preparation of the
decision.
DIGEST
Where solicitation required offerors to propose fixed prices and offeror
proposed pricing contingent upon "successful completion" of an agreement
with a third party, the offer was conditional and should not have been
considered for award.
DECISION
SunEdison, LLC protests the award of a contract to PowerLight Corporation
under request for proposals (RFP) No. FA4861-06-R-B501, issued by the
Department of the Air Force for the construction and operation of a
photovoltaic array to supply solar power to Nellis Air Force Base (AFB) in
Nevada. The protester contends that the agency's evaluation of offerors'
prices was flawed.
We sustain the protest.
BACKGROUND
The RFP explained that the agency's goal in awarding a contract under the
RFP was to reduce its unit cost for electrical service to Nellis AFB to
below the rate it was paying the Nevada Power Company, and, thus, if all
proposals received were for more than the cost of service from Nevada
Power, the government might elect not to award a contract. RFP sect.
B.2.3. The RFP also explained that a photovoltaic array produces both
renewable energy (solar power) measured in kilowatt-hours (kWh) and
renewable energy credits (REC), and that while the agency was aware that
an offeror would need to sell both outputs to have a viable project, the
government was interested in acquiring the kWh only.[1]
The RFP further explained that the contractor was to operate its solar
array, which was to be located on land leased to the contractor by Nellis,
"in parallel" with the electricity supplied to Nellis by the Nevada Power
Company from outside the base. RFP sections C.2.3.1, C.2.3.2. Accordingly,
offerors were required to furnish all equipment (e.g., inverters and
transformers) necessary to connect to the base electrical distribution
system. Offerors were also required to submit evidence with their
proposals that a request to Nevada Power for an interconnect agreement had
been made, with no contract to be awarded until an interconnect agreement
with Nevada Power had been secured.
The RFP provided for award to the offeror whose technically acceptable
proposal was determined to represent the lowest cost to the government.
Proposals were to be evaluated on a pass/fail basis with regard to four
"mission requirements" (performance plan, financial capability,
implementation plan, and quality plan) and with regard to past
performance. Price was to be the deciding factor in the selection of a
proposal for award from among those determined to be technically
acceptable.
The RFP's price schedule asked each offeror to furnish a projection as to
the monthly output (in kWh) of its proposed solar array and a fixed unit
price per kWh. The schedule also asked offerors for an escalation factor
to adjust subsequent year prices for inflation. The RFP explained that
total evaluated price would be the net present value of the stream of
monthly payments that the government would be expected to make to the
contractor over a projected contract term of 20 years. RFP sections
M.2.1.1, M.3.4. For purposes of the price evaluation, each monthly payment
was to be calculated by multiplying the offeror's projection of the output
of its proposed solar array in kWh by the offeror's proposed unit price
per kWh. RFP sect. M.3.4. The solicitation further explained that the
evaluated first year annual price would be the sum of the monthly payments
and that subsequent year annual prices would be calculated by multiplying
the previous year's annual price by the escalation factor proposed in the
schedule. Id.
Offerors were instructed to explain how they had derived their kWh price
in their proposals. In particular, they were instructed to furnish
information regarding "tax credits, other incentives, sale of RECs, [and
expenses for] operation and maintenance." RFP sect.
Full decision text continues on ProtestIntel...