B-299766; B-299766.2, Lockheed Martin Maritime Systems & Sensors, August 10, 2007
Case: B-299766
Agency:
Protester: B
Date: 2007-08-10
Sustained
B-299766; B-299766.2, Lockheed Martin Maritime Systems & Sensors, August 10, 2007
TITLE: B-299766; B-299766.2, Lockheed Martin Maritime Systems & Sensors, August 10, 2007
BNUMBER: B-299766; B-299766.2
DATE: August 10, 2007
*********************************************************************************
B-299766; B-299766.2, Lockheed Martin Maritime Systems & Sensors, August 10, 2007
DOCUMENT FOR PUBLIC RELEASE
The decision issued on the date below was subject to a GAO Protective
Order. This redacted version has been approved for public release.
Decision
Matter of: Lockheed Martin Maritime Systems & Sensors
File: B-299766; B-299766.2
Date: August 10, 2007
W. Jay DeVecchio, Esq., Kevin C. Dwyer, Esq., Edward Jackson, Esq., and
Daniel E. Chudd, Esq., Jenner & Block LLP, for the protester.
David P. Metzger, Esq., Kristen E. Ittig, Esq., Stuart W. Turner, Esq.,
and Caitlin K. Cloonan, Esq., Arnold & Porter LLP, for Chesapeake Sciences
Corporation, an intervenor.
Sabrina L. Hay, Esq., Jessica Clark, Esq., Michael J. Glennon, Esq.,
Andrew Saunders, Esq., and Alex F. Marin, Esq., Department of the Navy,
for the agency.
Paul N. Wengert, Esq., and Ralph O. White, Esq., Office of the General
Counsel, GAO, participated in the preparation of the decision.
DIGEST
Protest is sustained where solicitation provided for tow-off testing of
prototype arrays according to a procedure in which each offeror was
explicitly permitted to participate in installation and check-out of its
prototype, and then granted a single opportunity to repair any failure of
its prototype immediately prior to towed testing, but the agency did not
notify the protester that its prototype had already failed before arrival
at the testing site, and did not allow the protester to repair its
prototype, and as a result, the agency was unable to evaluate significant
aspects of the performance of the protester's array.
DECISION
Lockheed Martin Maritime Systems & Sensors protests the award of a
contract to Chesapeake Sciences Corporation by the Department of the Navy,
Naval Sea Systems Command (NAVSEA), under request for proposals (RFP) No.
N00024-05-R-6259, issued as a follow-on to development contracts awarded
under a broad agency announcement to procure production towed-arrays for
the TB-34 Next Generation Fat-Line Towed Array program. Lockheed argues
that the Navy failed to properly remedy a breach of procurement integrity,
did not follow the procedure for testing and evaluating prototype arrays
specified in the RFP, and made a defective source selection decision.
We sustain the protest.
BACKGROUND
The Navy conducted this competition for the production of towed arrays[1]
between the two contractors that had delivered prototypes of their own
design under separate contracts. Thus, the procurement process began in
September 2004 when, after competition among four firms under a broad
agency announcement, the Navy awarded separate contracts to Chesapeake and
Lockheed for each to develop a prototype of a next-generation towed array,
for a subsequent head-to-head competition for a production contract. Under
the prototype contracts, each contractor designed and delivered a
prototype of its array in October 2005.
The Navy experienced problems with both prototypes in mid-March 2006, and
returned each to the respective manufacturer for repairs from March 13 to
March 19, 2006.[2] Shortly thereafter, the Navy issued the RFP here on
March 23 to Chesapeake and Lockheed, requesting production offers. While
the RFP requested a technical proposal, the evaluation of the performance
of each offeror's prototype array, as discussed below, formed the basis
for a significant part of the technical evaluation. In this regard, it
should be noted that certain testing of the prototype arrays was ongoing
before and after issuance of the RFP for this competition.
The RFP described the non-price evaluation in terms of three factors:
technical performance, contractor statement of work, and past
performance.[3] RFP at 178. Of these three, the RFP specified that the
technical performance factor would be significantly more important than
the contractor statement of work and past performance factors combined. In
addition, the non-price factors were significantly more important than
cost/price. The RFP also made clear that the operation of the prototypes
would be a significant aspect of the technical performance evaluation. RFP
at 170-71.
The RFP described several stages of the evaluation of the protoypes,
including acoustic calibration, tow-off testing, and anechoic chamber
testing. These were described in a separate section of the RFP labeled
"Evaluation Plan for the Next-Generation Fat-Line Towed Array Testing."
RFP, Evaluation Plan, at 1.
Full decision text continues on ProtestIntel...