Perimeter Security Partners, LLC
Case: B-417591
Agency: Department of Defense : Department of the Army : Corps of Engineers
Protester: Perimeter Security Partners, LLC
Date: 2019-08-19
Denied
B-417591
Aug 19, 2019
Jump To
VIEW DECISION
DOWNLOADS
RELATED PAGES
GAO CONTACTS
Highlights
Perimeter Security Partners, LLC (PSP), a small business, of Brentwood, Tennessee, protests the cancellation of invitation for bids (IFB) No. W912DR-18-B-0005, issued by the Department of the Army, Corps of Engineers (Corps), for the construction of an access control point in Fort Meade, Maryland. PSP contends the Corps improperly concluded the bid prices received were unreasonable, cancelled the IFB, and converted the procurement to a negotiated procurement pursuant to Federal Acquisition Regulation (FAR) § 14.404-1(e)(1).
We deny the protest.
View Decision
DOCUMENT FOR PUBLIC RELEASE
The decision issued on the date below was subject to a GAO Protective Order. This version has been approved for public release.
Decision
Matter of: Perimeter Security Partners, LLC
File: B-417591
Date: August 19, 2019
David A. Rose, Esq., Rose Consulting, LLC, for the protester.
Maureen A. McAndrew, Esq., and Raymond Schlee, Esq., Department of the Army, for the agency.
Christopher Alwood, Esq., Evan D. Wesser, Esq., and Edward Goldstein, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.
DIGEST
Protest challenging the cancellation of an invitation for bids after bid opening and conversion to a negotiated procurement is denied where the agency reasonably found that the sealed bid prices were unreasonable where the low bid exceeded the government’s independent estimate by 23.5 percent.
DECISION
Perimeter Security Partners, LLC (PSP), a small business, of Brentwood, Tennessee, protests the cancellation of invitation for bids (IFB) No. W912DR-18-B-0005, issued by the Department of the Army, Corps of Engineers (Corps), for the construction of an access control point in Fort Meade, Maryland. PSP contends the Corps improperly concluded the bid prices received were unreasonable, cancelled the IFB, and converted the procurement to a negotiated procurement pursuant to Federal Acquisition Regulation (FAR) § 14.404-1(e)(1).
We deny the protest.
BACKGROUND
The Corps issued the IFB on June 15, 2018, pursuant to the two step sealed bidding procedures of FAR part 14, as a small business set-aside that contemplated the award of a fixed-price contract for construction of the Reece road access control point in Fort Meade, Maryland. The deadline for submission of bids for step one was July 24. Agency Report (AR), Tab 3, IFB amend. 2, at 1-2. The agency received five timely step-one bids, and the contracting officer subsequently determined that three bidders would advance to step two. AR, Tab 4, Down Select Memorandum, at 3. The deadline for submission of bids for step two was March 20, 2019 at 2:00 p.m. AR, Tab 7, IFB amend. 5, at 1.
The agency received three timely step-two bids, including from PSP. Combined Contracting Officer’s Statement/Agency Memorandum of Law (COS/MOL) at 1. The bids, and the agency’s independent government estimate (IGE), were as follows:
Bidders
Total Bid
Perimeter Security Partners
$26,505,208
Akima Construction Services
$26,508,587
AMG JV
$26,520,611
IGE
$21,460,936
AR, Tab 11, Bid Abstract.
On April 23, the contracting officer concluded that all of the bids were unreasonably high because they exceeded the IGE by between 23.5 and 23.58 percent. AR, Tab 13, Memorandum for Record, at 2. The contracting officer also decided that it was in the best interest of the government to cancel the IFB and complete the procurement through negotiation in accordance with FAR § 14.404-1(e)(1). Id. The Corps sent a letter to PSP dated May 10, which advised that all three bids had been determined to be unreasonable since they exceeded the IGE by “25.0% or more.” AR, Tab 14, Letter Cancelling Invitation for Bids, at 1. The letter also informed PSP that the Corps was cancelling the IFB and would attempt to complete the procurement through negotiation. Id. PSP submitted this protest to our Office on May 20.
DISCUSSION
PSP argues that the contracting officer improperly concluded that the bid prices received were unreasonable, and therefore lacked a compelling reason to cancel the IFB as required by FAR § 14.404-1(a)(1). Protest at 6. For the reasons that follow, we find no basis on which to sustain the protest.[1]
Once bids have been opened, award must be made to the responsible bidder who submitted the lowest responsive bid, unless there is a compelling reason to reject all bids and cancel the IFB. FAR § 14.404-1(a)(1). One such compelling reason an IFB may be canceled after bid opening is when the prices of all otherwise acceptable bids are unreasonable.
Full decision text continues on ProtestIntel...