A2A Integrated Logistics, Inc. (36C24425Q0297)
Case: B-423433
Agency: Department of Veterans Affairs : Department of Veterans Affairs
Protester: A2A Integrated Logistics, Inc.
Date: 2025-05-20
Dismissed
B-423433
May 20, 2025
Jump To
VIEW DECISION
DOWNLOADS
RELATED PAGES
GAO CONTACTS
Highlights
A2A Integrated Logistics, Inc., a service-disabled veteran-owned small business of Fayetteville, North Carolina, protests the award of a contract under request for quotations (RFQ) No. 36C24425Q0297, issued by the Department of Veterans Affairs (VA), for media systems and hardware, digitizing/document scanning software licenses, and onsite training services for the VA Wilkes-Barre Medical Center in Wilkes-Barre, Pennsylvania. The protester contends that its quotation represented the best value to the agency. The protester also contends that the agency's server improperly rejected its quotation.
We dismiss the protest because prior to protesting to our Office, the protester filed an agency-level protest and that protest was not timely filed.
View Decision
DOCUMENT FOR PUBLIC RELEASE
The decision issued on the date below was subject to a GAO Protective Order. This version has been approved for public release.
Decision
Matter of: A2A Integrated Logistics, Inc.
File: B-423433
Date: May 20, 2025
Anthony L. Bryant for the protester.
Natica Chapman Neely, Esq., Department of Veterans Affairs, for the agency.
Jacob M. Talcott, Esq., and Jennifer D. Westfall-McGrail, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.
DIGEST
Protest challenging the agency’s award of a contract and the rejection of the protester’s quotation by the agency’s server is dismissed where the protest was filed more than 10 days after the protester knew or should have known the basis for its protest.
DECISION
A2A Integrated Logistics, Inc., a service-disabled veteran-owned small business of Fayetteville, North Carolina, protests the award of a contract under request for quotations (RFQ) No. 36C24425Q0297, issued by the Department of Veterans Affairs (VA), for media systems and hardware, digitizing/document scanning software licenses, and onsite training services for the VA Wilkes-Barre Medical Center in Wilkes-Barre, Pennsylvania. The protester contends that its quotation represented the best value to the agency. The protester also contends that the agency’s server improperly rejected its quotation.
We dismiss the protest because prior to protesting to our Office, the protester filed an agency-level protest and that protest was not timely filed.
Our Bid Protest Regulations contain strict rules for the timely submission of protests. These rules reflect the dual requirements of giving parties a fair opportunity to present their cases and resolving protests expeditiously without unduly disrupting or delaying the procurement process. Verizon Wireless, B‑406854, B‑406854.2, Sept. 17, 2012, 2012 CPD ¶ 260 at 4. Under these rules, a protest based on alleged improprieties in a solicitation must be filed prior to bid opening or the time established for receipt of proposals, 4 C.F.R. § 21.2(a)(1), and all other protests must be filed no later than 10 calendar days after the protester knew, or should have known, of the basis for protest, whichever is earlier. 4 C.F.R. § 21.2(a)(2). Further, a matter initially protested to the contracting agency will be considered timely by our Office only if the initial agency protest was filed within the time limits provided by the Regulations for filing a protest with our Office unless the contracting agency imposes a more stringent time for filing, in which case the agency’s time for filing will control. 4 C.F.R. § 21.2(a)(3).
As relevant here, the solicitation provided that the closing date for quotations was February 10, 2025; the agency announced award on February 19. Req. for Dismissal, exh. 1, RFQ at 1; Req. for Dismissal at 2. On February 20, the protester emailed the contracting officer, stating that the protester was unable to submit its quotation. Req. for Dismissal, exh. 3, Agency Email at 1. The agency responded to the protester on March 12 and explained that it had not received the protester’s quotation. Id. The protester then filed an agency-level protest that same day; the agency dismissed the agency-level protest as untimely on March 27. Req. for Dismissal, exh. 4, Agency‑Level Protest at 1; Req. for Dismissal, exh. 5, Agency Dismissal at 4‑5. The protester filed this protest with our Office on April 1.
The protester challenges the agency’s award of a contract and the rejection of the protester’s quotation by the agency’s server. Protest at 1‑2. Concerning the challenge to the award of the contract, we dismiss this argument as untimely because the protester challenged the award more than 10 calendar days after it knew, or should have known, of the basis for protest. In this regard, the agency made award on February 19; the protester, however, did not formally challenge the award until it filed its agency‑level protest on March 12. Req. for Dismissal at 2.
Full decision text continues on ProtestIntel...